Monday, June 27, 2011

US 41 Project lane closures for June 26 – July 1

For more information contact:

Kris Schuller, US 41 Project communication manager
Kris.Schuller@dot.wi.gov (920) 492-4109


US 41 Project lane closures for June 26 – July 1

Traffic restrictions in Brown and Winnebago counties

(Green Bay) The Wisconsin Department of Transportation (WisDOT) Northeast Region in Green Bay is announcing US 41 lane restrictions for June 26 through July 1 in Brown and Winnebago counties. Traffic impacts in Brown County involve lane closures near Scheuring Road, WIS 172, Lombardi Avenue and WIS 29. Drivers in Winnebago County are reminded of 11-foot wide lanes and reduced speed limits on US 41 between WIS 26 and Breezewood Lane.

Winnebago County

WIS 26 – WIS 21

Monday, June 27:

Right lane of southbound WIS 26, between the north and southbound US 41 on-and off-ramps, closed starting Monday through July 22

Sunday, June, 26 – Thursday June 30:

Left lane of southbound US 41, between WIS 26 and County Z, closed Sunday through Thursday from 7 p.m. to 5 a.m., for work on the temporary concrete barrier wall.

Various lanes of northbound US 41, between County Z and WIS 21, closed Sunday through Thursday from 7 p.m. to 5 a.m., to switch northbound US 41 traffic to the newly constructed northbound lanes and to set temporary concrete barrier.

US 45 – Breezewood Lane

Tuesday, June 28 and Wednesday, June 29:

Left-turn lane of southbound WIS 76, between the north and southbound US 41 ramps, closed Tuesday and Wednesday from 9 a.m. to 2 p.m. , for work on the US 41 bridges over WIS 76.

Tuesday, June 28 – Thursday, June 30:

Various lanes of southbound US 41 off-ramp at WIS 76 and various lanes of southbound WIS 76,
from Indian Point Road to Green Valley Road, closed Tuesday through Thursday from 9 a.m. to 2 p.m., to allow work on the US 41 bridges over WIS 76

Brown County

Scheuring Road

Monday, June 27 – Thursday, June 30:

Various lanes of north and southbound US 41 at Scheuring Road closed Monday through Thursday, from 7 p.m. to 5 a.m., for construction of the new Scheuring Road interchange.

Various lanes of north and southbound US 41, from one mile south of Scheuring Road to Scheuring Road, closed Monday through Thursday from 7 p.m. to 5 a.m., for construction of temporary shoulders.

WIS 172

Monday, June 27 – Thursday, June 30:

Left lane of westbound WIS 172 , from US 41 to Babcock Road, closed Monday through Thursday from 6 p.m. to 6 a.m., for access to the median.

Left lane of eastbound WIS 172, from Babcock Road to US 41, closed continuously Monday through Thursday for access to the median.

Lombardi Avenue

Monday, June 27 – Thursday, June 30:

Various lanes of north and southbound US 41, between Lombardi Avenue and Mason Street, closed Monday through Thursday from 8 p.m. to 5 a.m., for construction of temporary shoulders.

WIS 29

Monday, June 27 – Thursday, June 30:

Various lane closures on east and westbound WIS 29, between Packerland Drive and County FF, to allow work in the median. The restrictions are in place Monday through Thursday, from 7 p.m. to 7 a.m.

Wednesday, June 29:

Various lanes of eastbound WIS 29, between Packerland Drive and Taylor Street, closed Wednesday from 7 p.m. to 5 a.m., to allow work in the median.

Various lanes of the north and southbound US 41 off-ramps at WIS 29 closed Wednesday from 7 p.m. to 5 a.m.

All lane restrictions are weather dependent and subject to change.