Friday, October 05, 2012

Weekly construction update


(Green Bay) The Wisconsin Department of Transportation (WisDOT) NE Regional Office in Green Bay is providing a weekly update on region construction, which includes the counties of Brown, Calumet, Door, Fond du Lac, Kewaunee, Manitowoc, Marinette, Oconto, Outagamie, Sheboygan, and Winnebago.

                  

Motorists are advised to use caution and remain alert when driving through any work zone.

Drivers are also encouraged to seek information about work zones and detours in the following ways:

  • For statewide, recorded road construction information, 24 hours a day, call 511.

·         For statewide road construction on the World Wide Web, visit www.511wi.gov

 

All work is weather dependent.

 


Brown County

Leo Frigo Bridge, city of Green Bay/ I-43

Schedule: May 2012 to July 2013

Length:  3.5 Miles

Cost:  $16.8 million

Location:  I-43 over the Fox River

Description:  Work consists of completing concrete deck surface repair and placing an asphalt or concrete overlay on I-43 over the Fox River, Atkinson Drive over I-43, and Military Avenue over I-43; replacing the bridge joints along I-43 over the Fox River and Military Avenue over I- 43; painting of the steel girders within ten feet of the joint replacements, the box girders along the arch span, and all steel within the splash zone along I-43 over the Fox River; concrete pavement repairs along I-43 between Webster Avenue and Military Avenue and along with the ramps at Webster Avenue and Atkinson Drive; traffic cameras at I-43/Danz Avenue, I- 43/University Avenue, and I-43/County JJ; dynamic message signs at I-43/Glenmore Road, I- 43/Danz Avenue, I-43/Military Avenue, and I-43/WIS 54/57; ramp gates at the Webster Avenue and Atkinson Drive on-ramps to I-43; temporary and permanent storm sewer; beam guard replacement; median concrete barrier wall; sign replacement; and pavement markings.

October 1 to October 5: Contractor continued work on the modular joints, they continued blast cleaning and painting the outside steel girders, they finished the parapet wall surface repair, and they finished replacing the pins and hangers along I-43 southbound over Leo Frigo Bridge.

October 8 to October 12: Contractor will continue work on the modular joints and blast cleaning and painting the outside steel girders along I-43 southbound over Leo Frigo Bridge; they will switch traffic to be directional along the Atkinson Drive southbound lanes and will begin work on the deck surface along the Atkinson Drive northbound lanes; and they began placing the final pavement marking throughout the project limits.

Traffic Impacts: I-43 northbound and southbound is now bi-directional along the I-43 northbound lanes. The on-ramp from Webster Avenue to I-43 northbound, the on-ramp from Atkinson Drive to I-43 southbound, and the off-ramp from I-43 southbound to Webster Avenue are closed to all traffic. Starting October 8, traffic along Atkinson Drive will be reduced to one lane in each direction and will be counter-directional along the southbound lanes between the railroad overpass and Hurlbut Street.

 

US 41 Orange Lane to Glory Road, Main Avenue (County G) Interchange

Schedule: March 2012 through June 2013.  The Main Avenue (County G) interchange will be closed for 60 consecutive days beginning September 17, 2012.

Length: Mainline -3.5 miles (Orange Lane - Glory Road); Main Avenue (County G) - 0.5 miles (Spirit Way - Lawrence Drive)

Cost: $57 million

Location: Town of Lawrence, city of De Pere, village of Ashwaubenon; Brown County

Description of project: This project will reconstruct US 41 Mainline between Orange Lane and Glory Road and the reconstruction of the Main Avenue interchange and replacement of bridges over Ashwaubenon Creek, Main Avenue, and Grant Street.

October 1 to October 5:  The contractor will begin outside mainline grading and structure work made available after the switch to stage 2.  Retaining wall work will continue along the Ashland Avenue ramp.  Work on the barrier wall and shoulders of this ramp will also continue.  On County G, aggregate placement, concrete placement, storm sewer, and sign structure work will continue.

October 8 to October 12:  The contractor will continue outside mainline grading and structure work from Orange Lane to Glory Road.  On County G, the contractor will continue placing concrete pavement and curb and gutter.  Work will begin on County EE bridges and retaining walls.

Traffic impacts: US 41 northbound and southbound shoulders closed from March 5, 2012 to June 21, 2013 from 1.5 miles south of Scheuring Road to Parkview Road.  US 41 northbound and southbound lanes are restricted to 11 feet from 1.5 miles south of Scheuring Road to Parkview Road with speeds reduced from 65 mph to 55 mph within the project limits and north through the Mason Street Interchange project.  As of March 27, east and westbound traffic on County G are reduced to one lane each direction. Beginning on September 17 at midnight, the County G interchange will close for 60 days.  The closure will include the north and southbound on/off ramps to US 41, as well as County G itself from just west of the Mid Valley Drive intersection to a point just west of the Lawrence Drive intersection. Mid Valley Drive will also be closed at County G with no access to County G. The left shoulder of the northbound off-ramp to Oneida Street will be closed until October 19.  The left lane of the southbound off-ramp to Scheuring Road will be closed until October 12.  County EE (Grant Street) will be closed under US 41 on October 3, 4, 9, and 10 from 9 p.m. to 5 a.m.  Both shoulders of Glory Road from US 41 to 1000 feet in both directions will be closed until October 19. The northbound and southbound outside lanes will be closed from 8 p.m. to 5 a.m. on the night of October 3.  The southbound outside lane will be closed from 8 p.m. to 5 a.m. on the nights of October 5, October 8 through 13, and October 15 and 20.  The southbound on-ramp for Ashland Avenue will be closed from 8 p.m. to 5 a.m. on the night of October 5.

US 41 (Early Structures/Early Fills), (Beaver Dam Creek Box Culvert at Van Boxtel), (Wetland Mitigation Site Resort Road) – US 41 major

Schedule: June 2011 to October 2012

Length:  0.8 Miles

Cost:  $38.2 million

Location:  US 41/WIS 29 Interchange, County J - village of Suamico

Description: The work under this contract consists of common excavation; borrow excavation, construction of various structures, storm sewer, culverts, and erosion control.

October 1 to October 5: Continue forming and pouring anchor slabs and parapets. Continue to place miscellaneous storm sewer pipes and manholes. Continue staining the pre-stressed concrete panels. Continue final restoration where staging allows.

October 8 to October 12: Continue forming and pouring last remaining parapets. Continue staining the pre-stressed concrete panels. Continue final restoration and work on punch list items.

Traffic Impacts:  No more traffic impacts all major work is complete.

 

US 41/ WIS 29 Interchange Core Project - US 41 major

Schedule: August 2012 to October 2014

Length: 1.6 miles along US 41, 0.8 miles along WIS 29

Cost: $97 million

Location: US 41 (Mason Street to Memorial Drive)/ WIS 29 (County J to Taylor Street)

Description: This project will complete the reconstruction of the US 41 and WIS 29 interchange, converting the interchange by building high speed, free flow flyover ramps, along with adding capacity to US 41. Included in this project is the construction of 12 bridges, 15 retaining walls, 30 sign bridges, concrete pavement, asphalt pavement, storm sewer, stormwater detention ponds and landscaping, while incorporating many community sensitive design features.

October 1 to October 5: Crews will continue bridge pier construction in the US 41 median south of Shawano Avenue and north of Dousman Street, along with pier construction along the east side of US 41 between Larson Road and Shawano Avenue. Crews will continue the construction of soil improvements along the east and west side of US 41 north of Memorial Drive.  At night crews will continue widening the median to allow for temporary pavement, as well as some pours at night at the median flyover bridge piers.  Crews will continue removing pavement and installing drainage blanket in the old WIS 29 areas, along with wick drain installation. Traffic will be shifted toward the median on northbound and southbound US 41 to allow for the construction of the new US 41 bridges over Memorial Drive. Bridge crews have also began the construction of the piers at the new WIS 29 bridges over Packerland Drive.

October 8 to October 12: Crews will continue bridge pier construction in the US 41 median south of Shawano Avenue and north of Dousman Street, along with pier construction along the east side of US 41 between Larson Road and Shawano Avenue. Crews will continue the construction of soil improvements along the east and west side of US 41 north of Memorial Drive.  Retaining wall crews will continue construction of the retaining wall on the east side of US 41, from the south project limits to Larson Road. At night crews will continue widening the median to allow for temporary pavement, as well as some pours at night at the median flyover bridge piers.  Crews will continue removing pavement and installing drainage blanket in the old WIS 29 areas, along with wick drain installation. Bridge crews will also continue the construction of the piers at the new WIS 29 bridges over Packerland Drive.

Traffic Impacts: Lane closures are scheduled for US 41 northbound and southbound traffic Tuesday through Friday nights.

 

US 41/WIS 29/County J Structures and County RK (South Frontage Road) West

Schedule: June 2011 to August 2012

Length:  1.1 Miles

Cost:  $10 million

Location:  WIS 29/County J and WIS 29 South Frontage Road, County J to Duck Creek

Description:  Work consists of building new structures along WIS 29 at County J with aesthetic details and under deck lighting; reconstructing County J from Berkshire Drive to Shawano Avenue to go under WIS 29 with street lighting, sidewalks, and plantings; constructing a single lane roundabout at the intersection of County J and new County RK (South Frontage Road); and constructing a new urban roadway (County RK) with sidewalk along the south side of the roadway, street lighting, and plantings.

October 1 to October 5: Contractor finished staining the concrete surfaces along the bridges and retaining wall and they completed the final landscaping along County J.

October 8 to October 12: Contractor will install the final plantings throughout the County J and County RK roundabout.

Traffic Impacts: Shoulders closures along County J under WIS 29.

 

WIS 29 - County EB Ramps, County RK Park and Ride, Duck Creek Bridges

Schedule: February to November

Length: 2 miles total at various locations adjacent to the WIS 29/US 41 interchange

Cost: $18 million

Location:  Green Bay, WI, Brown County

Description:  Project includes the construction of the eastbound and westbound County EB on and off ramps at WIS 29, widening of WIS 29 eastbound and westbound, building structures over Duck Creek, construction of Shawano Avenue and temporary connections at Dousman and the US 41 ramp terminals at Shawano Avenue, temporary ramps at US 41 and Shawano Avenue, realignment of Beaver Dam Creek, and a Park and Ride at County RK.

October 1 to October 5: Aggregate placement will occur west of Duck Creek.  Construction of the Duck Creek bridge abutments will begin. Storm sewer installation will continue, and gravel will be placed at the Shawano Avenue connection. Curb and gutter will also be installed at the Shawano Avenue connection.

October 8 to October 12:  Work will finish digging Beaver Dam Creek for realignment.  Work will continue on the piers in Duck Creek.  Asphalt base will be placed west of Duck Creek. Work will begin to remove the railroad tracks on County EB south of County RK.  Vane drain installation will occur.

Traffic Impacts: There will be daily inside lane closures on WIS 29 west of County EB/Packerland Drive. There will be also be various shoulder and lane closures on WIS 29 next week during the day and evening.  Expect daily westbound and eastbound WIS 29 lane closures. There were many changes in pavement marking, barrier wall, signing, and traffic patterns that occurred in the beginning of the week on WIS 29, County EB (Packerland Drive/ /Cardinal Lane), Dousman Street, Shawano Avenue, and the US 41 ramps.  The traffic pattern adjacent to the Cardinal/Packerland/County EB and WIS 29, as well as US 41 and Dousman/Shawano has changed considerably. Please drive with caution, and plan for slight delays accordingly. There will be outside lane closures on Packerland Drive/County EB on Tuesday night at the railroad tracks to begin track removal.  These closures will be allowed between the hours of 6 p.m. Tuesday night and 6a.m. Wednesday morning.

 

Mason Street Interchange and 9th Street to Larsen Road Mainline - US 41 major

Schedule: September 2011 to October 2012

Length: 1.0 Mile

Cost: $29 million

Location: Mason Street Interchange and US 41 Mainline from 9th Street to Larsen Road.

Description: This project will reconstruct the Mason Street Interchange with new ramps, bridge over US 41, roundabout ramp terminals, and retaining walls. The project also includes the complete reconstruction of the US 41 mainline through the Mason Street Interchange vicinity, from just south of 9th Street to just south of Larsen Road. Mainline includes the paving of mainline to the ultimate roadway section including the replacement of the 9th Street bridges, box culverts, retaining walls, and storm sewer. The project further includes the razing and removal of the Allied Pool building and subsequent construction of a detention pond on that site. 

October 1 to October 5: Minor work will continue on the structures, retaining walls and electrical/lighting installations.  General landscaping and finishing work will continue.

October 8 to October 12:  Minor work continues on the structures, retaining walls and electrical installations.  Landscaping and finish work continue.

Traffic impacts:  US 41 and Mason Street are open to traffic.  There are no anticipated traffic impacts for the week October 8 to October 12.

 

Temporary Signals- Packerland Drive/ Dousman Street/ Shawano Avenue

Schedule: November 2011 to October 16, 2015

Length: Nine intersections

Cost: $516,000

Location: Packerland Drive/ Dousman Street/ Shawano Avenue Intersections - Green Bay, WI

Description: This contract shall consist of installing and operating temporary traffic signals and all incidental items.

Traffic impacts: No traffic impacts - work being done off alignment.

 

Velp Avenue (US 141), City of Green Bay

Schedule: April 2012 to September 2012

Length:  1.7 Miles

Cost:  $6.1 million

Location:  Velp Avenue from Norwood Avenue to Military Avenue, Atkinson Drive from Velp Avenue to the I-43 Interchange

Description:  Work consists of grading, storm sewer, base aggregate dense, concrete pavement, asphalt pavement, concrete sidewalk, wall modular block gravity, pavement marking and the construction of a roundabout at the intersection of Atkinson Drive and Velp Avenue. 

October 1 to October 5:  The contractor poured sidewalk, installed street lighting, and placed topsoil.

October 8 to October 12:  The contractor will be installing landscaping and trees, paving asphaltic driveways and parking lots.

Traffic Impacts: Velp Avenue traffic will be reduced to the one lane in both northbound and southbound directions from Military Avenue to Norwood Avenue. Atkinson Drive will be reduced to one lane in both the westbound and eastbound directions from Velp Avenue to the Interstate 43 interchange.  All side roads along Velp Avenue from Military Avenue to Norwood Avenue will remain open to traffic.

 

WIS 96 (Wrightstown)

Schedule: September 10, 2012 to October 22, 2012

Length:  2.1 Miles

Cost:  $1.1 million

Location:  WIS 96, Shanty Road to Lagoon Road

Description:  This project involves asphalt pavement milling, asphalt pavement overlay, shoulder widening, guardrail replacement, terminal upgrades, culvert pipe replacement, and pavement marking.

October 1 to October 5: The contractor completed shoulder grading and re-ditching along WIS 96.  Asphalt paving continued on eastbound and westbound lanes of WIS 96.  Pavement marking and restoration of slopes continued.

October 8 to October 12: The contractor will continue paving mainline WIS 96 and begin sideroad/driveway tie-ins.  Shoulder shaping will continue along eastbound and westbound WIS 96.  Work will begin on the installation of new guardrail along shoulders.

Traffic impacts:   During paving operations traffic will be reduced to one lane with flagging.  Access will be maintained to local businesses, residences and side road cross traffic throughout the project. Shoulders along eastbound and westbound WIS 96 will remain closed for the duration of the project.

 

Brown/Outagamie County


 

WIS 54

Schedule: April 2012 to mid-November 2012

Length:  1.0 Miles

Cost:  $8.74 million

Location:  WIS 54 from Oneida to Green Bay, County U to WIS 172

Description:  This project involves the realignment of WIS 54 with a new bridge over Duck Creek and construction of a roundabout at the intersection of WIS 54 and Seminary Road.  Work includes storm sewer, asphalt pavement, construction of a retaining wall, bridge rehabilitation, lighting, signing, landscaping and pavement marking.

October 1 to October 5:  Crews continued grading operations along WIS 54. Strom sewer continued through the week along WIS 54. Landscaping crews began placing topsoil and started seeding along the length of the project.  Staining work continued on the abutments of the new structure of WIS 54 over Duck Creek. Rehabilitation work began on the old structure of WIS 54 over Duck Creek. Electrical work continued for the pedestrian paths along WIS 54 and at roundabout at the intersection of WIS 54 and Seminary Road.

October 8 to October 12:  Grading operations along WIS 54 will continue through the week.  Storm sewer will be placed early in the week along portions of WIS 54. Landscape crews will continue to place topsoil and seed along WIS 54.  Rehabilitation work on the old structure of WIS 54 over Duck Creek will continue through the week. Electrical work will continue along the pedestrian paths through the week. 

Traffic Impacts:  Traffic along WIS 54 will remain open at all times, although brief periods of flagging may occur that will cause delays to the traveling public.  An all-way stop condition is in place for the intersection of WIS 54 and Seminary Road.  Traffic along WIS 54 is shifted to the north to allow for construction on the new lanes of WIS 54 and the south portion of the roundabout at the intersection of WIS 54 & Seminary Road. Please note traffic is now routed over the new structure of WIS 54 over Duck Creek.  Portions of WIS 54 have been reduced to 10-foot lanes to allow for construction activities. The south leg of Seminary Road is closed to thru traffic and will remain closed until late October for the construction of the WIS 54 and Seminary Road roundabout. West Service road is closed and will remain closed until mid to late October. 

 

Calumet County

 

US 10/City of Brillion

Schedule: April 2012 to October 2012

Length: 1.9 miles

Cost: $6.0 million

Location: County HR to eastern city limits – Brillion

Description: The project is an urban reconstruct project involving earthwork excavation, base aggregate, asphalt pavement, concrete pavement, sanitary sewer, storm sewer, curb and gutter, pavement marking, permanent signing, signals, and landscaping.

October 1 to October 5:  Pavement removals, grading and placement of breaker run and base aggregate will continue between County HR and the un-named tributary to Spring Creek. Concrete paving has started in the westbound lane from Columbus Avenue to Northway Drive.

October 8 to October 12: The contractor is scheduled to begin concrete pavement preparation from Columbus Avenue to Northway Drive in the eastbound lane after traffic is switched to the new concrete pavement.  Removals, grading, breaker run and base aggregate is scheduled between County HR and the un-named tributary to Spring Creek.  Sidewalk, driveway and intersection work on the north half of US 10 is scheduled to begin between Columbus Avenue and Northway Drive.

Traffic impacts: The project is closed to through traffic. A detour route is in place. The detour route will follow US 10 to WIS 57 to County K to County PP to US 10.  One-Way westbound access will be maintained to local businesses and property owners.

 

Calumet/Manitowoc County

 

Region-wide rumble strip retrofit

US 10

Schedule: October 1, 2012 until November 2, 2012

Length: Approx 34 miles

Cost: $1.8 million (total for awarded contract)

Location: County N to I-43

October 5 to October 6:  Installation of centerline rumble strips

October 8 to October 13: Complete the installation of rubble strips, and begin joint sealing and Installation of pavement marking 

Traffic impacts: Work will be conducted under a flagged rolling lane closure from 7 a.m. to 7 p.m. Traffic should be prepared for delays.

 

Door County


 

Region-wide rumble strip retrofit

WIS 42

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 16 miles                                                     

Cost: $1.8 million (total for awarded contract)

Location: Egg Harbor – Sturgeon Bay

October 4 to October 5:  Installation of centerline rumble strips

October 8 to October 12:  Joint sealing and the installation of pavement markings

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Fridays 7a.m. – noon.  Traffic should be prepared for delays.

 

Fond du Lac County

 

WIS 67
Auburn Lake Creek Culvert
Schedule: July 17 to October 2012
Length:  0.29 miles
Cost: $634,000
Location:  Birchwood Drive – County G, Fond du Lac County
Description: Primary work to be performed includes box culvert and retaining wall construction, grading, asphaltic paving and guardrail at structure approaches.

October 1 to October 5: Crews completed asphalt paving and placement of shoulder material. Crews continuing concrete barrier wall construction.

October 8 to October 12: Crews are scheduled to install beam guard, place permanent erosion control and pavement marking.

Traffic Impact: WIS 67 will be closed to through traffic beginning July 17. Detour route will be County SS to County G.

 

WIS 175
Parson’s Creek Culverts
Schedule: July 17 to October 2012
Length:  0.13 miles
Cost: $391,000
Location:  County B (East) – Lost Arrow Rd, Fond du Lac County
Description: Primary work to be performed includes construction of box culverts, grading, asphaltic paving and guardrail at structure approaches.
September 24 to September 28: Crews continued construction of the box culvert.

October 1 to October 5: Crews are scheduled to continue box culvert construction, place riprap and backfill structure

October 1 to October 5: Crews continued construction of the box culvert.

October 8 to October 12: Crews are scheduled to continue box culvert construction, place riprap and backfill structure.

Traffic Impact: WIS 175 will be closed to through traffic beginning July 17. Detour route will be County B to US 41 to US 151.

 

Marinette County

 

Region-wide rumble strip retrofit

US 141/ US 8

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 20 miles

Cost: $1.8 million (total for awarded contract)

Location: Wisconsin-Michigan State line to County R; County K to Division St. (Wausaukee)

October 1 to October 5:  Installation of pavement marking

October 8 to October 12:  Installation of pavement marking

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m .– 7 p.m., and Fridays 7a.m. – noon.  Traffic should be prepared for delays.

 

US 41

Schedule:  June 11, 2012 to October 10, 2012

Length:   2.1 miles

Cost:  $3.8 million

Location:  South Doland Avenue to Old Peshtigo Road, City of Peshtigo,

Marinette County

Description: This project involves the removal and replacement of the existing bridge over the Peshtigo River. Also included is milling of the existing asphalt roadway and paving asphalt pavement at the same depth. Existing concrete pavement on the east side of the city will be diamond ground to provide a better riding surface. Existing sidewalk ramps are being replaced.

October 1 to September 5: Structure crews will continue work on the parapets on the bridge. Curb and gutter will be placed on the roadway on either side of the bridge. Electrical conduit will be installed behind the curb and gutter. New sidewalk will be poured late in the week on the roadway approaches to the bridge.

October 8 to October 12: Concrete sidewalk will be finished early in the week. The asphalt pavement on the approaches to the bridge will be placed during the early/mid portions of the week followed by pavement marking. Structure crews will clean-up the bridge deck and install the railing on the bridge.

Traffic impacts:  US 41 will be closed between Front Street and Pine Street in the city of Peshtigo for the duration of the project for bridge construction. Recommended alternate route is to use US 41 bypass of Peshtigo via the County Y and Business 41 ramps. The intersection of US 41 and Pine Street will be closed during work activities at the intersection. The alternate route will be to use Beebe Avenue between Pine Street and US 41.

 

US 141

Schedule:  May 21, 2012 to October, 2012

Length:   6.5 miles

Cost:  $3.9 million  

Location:  Amberg to Beecher, Marinette County

Description: This project involves the pulverizing and re-laying of 6.5 miles of US 141 from Amberg to Beecher, including the addition of a northbound and southbound passing lanes, intersection improvements, and culvert replacements. This project also includes new pavement, concrete curb and gutter, sign replacement, and pavement marking.

Sept 30 to Sept 06: The contractor is working on pavement markings and punch list items.

Oct 07 to Oct 13: The contractor will be working on punch list items.

Traffic impacts:  US 141 will be maintained under the guidance of standard flagging operations, but will be open to through traffic during construction operations, throughout the duration of the project.

 

Manitowoc County

 

US 151/ I-43

Schedule: August to October  

Length: N/A miles

Cost: $580,000

Location: US 151 and I-43 Interchange

Description of project: The work under this contract consists of widening the southbound and northbound entrance ramps, various pavement repair and replacement on all four ramps at the interchange and median work on US 151.

.October 1 to October 6: contractor will be paving asphalt shoulder on northbound US 151. Contractor will be installing concrete pavement in ramp widening areas.  Contractor will also be completing electrical installations.  New pavement markings will be placed.  Site restoration will begin.

October 8 to October 12: Contractor will continue installing concrete pavement in ramp widening areas.  New pavement markings will be placed. Site restoration and clean up will be done.  Contractor will install new signage. 

Traffic impacts:  US 151 will be restricted to at least one 12-foot-wide lane in each direction on the overpass. Ramp widths will be restricted to 12-foot-wide lanes once the ramp work begins. There will be no impacts on the I-43 through traffic. 

 


Oconto County


 

WIS 22

Schedule:  June 4 to mid-November

Length:   Eight miles

Cost:  $7.4 million

Location:  Gillett to Oconto Falls

Description: The highway is being reconstructed between Gillett and Oconto Falls.  Additionally, a single-lane roundabout will be built at the WIS 22/32 intersection. 

October 1 to October 5:  Contractor continued paving mainline and intersections from Gillett to Oconto Falls.  Contractor installed electrical conduit and concrete bases at WIS 22/32 roundabout and WIS 22/32 West Junction.

October 8 to October 12:  Contractor will continue paving mainline and intersections from Gillett to Oconto Falls.  Contractor will begin to place final shoulder gravel from Gillett to Oconto Falls.  Contractor will complete traffic lighting and electrical installations at WIS 22/32 roundabout and WIS 22/32 West Junction.

Traffic impacts:  WIS 22 is closed from Gillett to Oconto Falls. This closure will close both WIS 22 and WIS 32 to through traffic and the detour is posted.  Going north on WIS 22, the detour will start at County C in Pulcifer to County E, US 141, and WIS 22.  Going south, it is the same route in reverse.  Northbound on WIS 32, the detour will start at County E, County C, WIS 22, and WIS 32 in Gillet.  Going south, it is the same route in reverse.  Access will be maintained to local businesses, residences and side road cross traffic throughout the project. 

 

Region-wide rumble strip retrofit

WIS 32

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 40 miles                                                     

Cost: $1.8 million (total for awarded contract)

Location: Forest/ Oconto County line - Gillett

October 1 to October 6:  Joint sealing and installation of pavement marking

October 8 to October 12:  Continue with the installation of pavement markings

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Fridays 7a.m. – 3 p.m. Saturdays 7 a.m. – 5 p.m.  Traffic should be prepared for delays.

 


Outagamie County


 

WIS 55

Schedule: July to November   

Length: 0.2 miles

Cost: $1.3 million

Location: WIS 55 and County CE Intersection

Description of project: The work under this contract consists of constructing a multilane roundabout at the intersection of WIS 55 and County CE. 

October 1 to October 5: The contractor placed asphalt on the west half of the intersection.  Underground electrical installation continued.  Sidewalk construction began on the west half of the intersection.  Preparation for the next traffic stage also began.

October 8 to October 12:  The traffic will be switched to next stage, at which time the intersection will be operating as a single lane roundabout. Temporary pavement will be removed on the north and south sides of the intersection and curb and gutter will be finished.  Curb and gutter and pavement will be placed in the center circle of the roundabout.  One single night closure will be occurring during this week. 

Traffic impacts:  WIS 55 will be restricted to one lane in each direction for the duration of the project.  County CE will be closed at the intersection. Traffic on County CE has access to WIS 55 from the east while traffic from the west does not. The marked detour route is County CE to County N to County KK to County GG to County CE. Access will be maintained to local businesses and residents. Traffic will be switched early next week. At that time, the intersection will be operating as a single lane roundabout. There will be a one night closure of the entire intersection during the week. 

 

WIS 96 (Draper Street, City of Kaukauna)

Schedule: Early April to October 2012   

Length: 0.9 miles

 Cost: $2.3 million

Location: West Kaukauna City Limits to WIS 55 (Lawe Street)

Description of project: This project will reconstruct WIS 96 (Draper Street/Taylor Street) between the west Kaukauna city limits and WIS 55 (Lawe Street). This reconstruction includes new concrete pavement, concrete curb and gutter, storm sewer, grading, sidewalk, pavement marking, and signing.  Stage 1 work will be from Hayes Street to Desnoyer Street. 

October 1 to October 5:  Landscaping and signing work was done by the contractor.  Pavement marking was also started.  The contractor also worked on clean-up and punchlist items.

October 8 to October 12: The contractor will be placing pavement marking and working on clean-up and punchlist items.

Traffic impacts:  WIS 96 (Draper Street/Taylor Street) will be closed to thru traffic from Hayes Street to Desnoyer Street.  Business access will be maintained via side streets. The marked detour will be via County N, County OO, and WIS 55.

 

Region-wide rumble strip retrofit

WIS 15

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 14 miles

Cost: $1.8 million (total for awarded contract)

Location: US 45 to Greenville

October 1 to October 5: Installation of centerline and shoulder rumble strips and begin joint sealing

October 8 to October 12: Continue joint sealing and installation of pavement markings

Traffic impacts: Work will be conducted under a flagged rolling lane closure Monday – Friday 9 a.m. to 3 p.m., Traffic should be prepared for delays.

 

Region-wide rumble strip retrofit

WIS 47

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 10 miles

Cost: $1.8 million (total for awarded contract)

Location: County B to Mackville

October 1 to October 5: Installation of centerline and shoulder rumble strips and begin joint sealing

October 8 to October 12: Continue joint sealing and installation of pavement markings

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Friday 7a.m. – noon.  Traffic should be prepared for delays.

 

Sheboygan County

 

WIS 57/WIS 23

Schedule: August 2012 to October 2012

Length: 24 Miles

Cost: $1.6 million

Location: Sheboygan County – Ozaukee/Sheboygan County Line to Manitowoc/Sheboygan County Line

October 1 to October 5:  Work continued on the WIS 57 northbound bridge deck replacement over the Onion River.  Work also continued on the WIS 23 eastbound bridge over the Sheboygan.  At the Intersection of WIS 57 and County C storm sewer installation and grading were completed

October 7 to October 12:  Work will continue on the WIS 57 northbound bridge deck replacement over the Onion River. Work will also continue on the WIS 23 eastbound bridge over the Sheboygan River.  At the intersection of WIS 57 and County C concrete curb and gutter and concrete pavement will be placed.

Traffic impacts: 

·         WIS 57 is open to through traffic.

·         WIS 57 has single lane closures in place near the intersection of County C. 

·         The intersection of WIS 28/57/County V has these restrictions:

o   WIS 28 eastbound will be closed at WIS 57.  Motorists will continue to have complete access up to the intersection of WIS 28 and WIS 57 from the west, but will be unable to make left turn on to WIS 57 north, continue east on WIS 28, or continue east on County V. WIS 28 eastbound traffic will be able to make a right turn on to WIS 57 southbound.  WIS 28 traffic coming from the west and heading east wanting to access WIS 57 northbound or continue on WIS 28 eastbound will be detoured from WIS 28 to County W to WIS 57. 

o   Traffic will be unable to turn left onto WIS 28 westbound from WIS 57 northbound.  (Traffic will be able to access WIS 28 westbound from WIS 57 southbound.)

o   Traffic will be unable to access WIS 57 from County V westbound

o   Traffic will be unable turn left onto County V eastbound from WIS 57 southbound. (Traffic will be able to access County V eastbound from WIS 57 northbound.)   

·         WIS 23 traffic is restricted to one lane in the eastbound direction near County TT 

 

Winnebago County

WIS 21 Interchange and US 41 reconstruction over Lake Butte des Morts - US 41 major

Schedule: August 2011 to July 2013

Length: 2 miles

Cost: $54.2 million

Location: WIS 21 Interchange, US 41 mainline from 1500 feet north of Witzel Avenue, to the US 45 Interchange.

Description: This project involves the reconstruction of the WIS 21 interchange to pass over US 41. The interchange will be completely reconstructed to include roundabouts at ramp terminals and at the WIS 21 intersections with Washburn and Koeller Streets. This project also includes the reconstruction of mainline US 41 from Witzel Avenue to the US 45 Interchange including new bridges over Lake Butte des Morts and Sawyer Creek. The work on the Lake Butte des Mort Causeway will include a recreational trail along the east side of US 41 crossing over the water.

September 29 to October 6:  Crews continued building retaining walls on the northeast corner of the WIS 21 interchange and continue grading for the new northbound US 41 lanes between WIS 21 and US 45.  Crews finished pier construction and began girder erection on the north and south channel bridges for northbound US 41, and began cofferdam construction at the main channel bridge.  Crews continued installing concrete pavement on the northbound US 41 lanes between Witzel Avenue and Lake Butte des Morts and on WIS 21 east of US 41.  Crews began landscaping the center roundabout islands at Washburn and Koeller Streets.

October 7 to October 13:  Crews will continue building retaining walls on the northeast corner of the WIS 21 interchange and continue grading for the new northbound between WIS 21 and US 45.  Crews will continue girder erection and cofferdam construction for the new northbound US 41 bridges on the Lake Butte des Morts causeway.  Crews will finish installing concrete pavement on the northbound lanes of US 41 between Witzel Avenue and Lake Butte des Morts as well as on the ramps and roundabout for the northbound US 41 ramps at WIS 21.  Crews will begin sidewalk installation on WIS 21 east of US 41.

Traffic impacts: The northbound and southbound shoulders of US 41 are closed between US 45 and Witzel Avenue. Northbound and southbound US 41 is reduced to two 11-foot lanes in each direction between US 45 and Witzel Avenue.  WIS 21 is closed to through traffic between US 41 and Koeller Street.  The signed detour to WIS 21 from US 41 will use the WIS 44/WIS 91 interchange.  WIS 21 is open west of US 41 only.  Westbound WIS 21 traffic in the city of Oshkosh will continue to utilize the WIS 44 signed detour for access to US 41.  Eastbound WIS 21 traffic approaching US 41 will utilize southbound US 41 to WIS 44 to access northbound US 41.

             

US 41 – Mainline (US 45 to Breezewood Lane)

Schedule: March 2011 to June 2013

Length: 8.0 Miles

Cost: $45 Million

Location: US 41 - US 45 Interchange to Breezewood Lane

Description: This project involves the reconstruction and widening of US 41.  The work includes construction of multiple structures including: bridges, box culverts, and sign bridges along with grading, base aggregate, concrete & asphalt pavements, concrete barrier wall, and pavement marking.

September 30 to October 6: Concrete pavement was completed in all of the driving lanes.  There are several areas where the median pavement will be constructed in the next stage (November). Work on the median concrete barrier and light pole bases continued from WIS 76 to County G.

October 7 to October 13: Work will continue in the median.  Crews will be installing light pole bases and barrier wall from County GG to Breezewood Lane. Work will begin on the outside shoulder of the new northbound lanes.  Crews will begin constructing the asphalt and gravel shoulders from WIS 76 to Breezewood Lane. Type I (Large) sign bases and supports will be installed between WIS 76 and Breezewood Lane. Crews will begin painting the edge lines and installing grooved in contrast tape skips.

Traffic impacts:   Trucks are required to use the Left Lane thru the work zone due to the vane drains in the right lane which cause a bumpy ride.  The speed limit for both northbound and southbound traffic has been reduced to 55 mph and will remain that way until November 2012.  The northbound traffic continues the temporary lanes. The emergency stopping area for northbound traffic near Nee-Vin Road has been closed. The emergency stopping area near County GG will remain open. The on and off ramps to WIS 76 and Breezewood/Bell Street remain open. Please observe the advisory speed limits posted on the ramps.

0 Comments:

Post a Comment

<< Home