Weekly construction update
(Green
Bay) The Wisconsin Department of Transportation (WisDOT) NE Regional Office in
Green Bay is providing a weekly update on region construction, which includes
the counties of Brown, Calumet, Door, Fond du Lac, Kewaunee, Manitowoc,
Marinette, Oconto, Outagamie, Sheboygan, and Winnebago.
Motorists are advised to use caution and
remain alert when driving through any work zone.
Drivers
are also encouraged to seek information about work zones and detours in the
following ways:
- For statewide, recorded road
construction information, 24 hours a day, call 511.
All work is weather
dependent.
Brown County
Leo Frigo Bridge, city of Green Bay/ I-43
Schedule: May 2012 to July 2013
Length: 3.5 Miles
Cost: $16.8 million
Location: I-43 over the Fox
River
Description: Work consists of
completing concrete deck surface repair and placing an asphalt or concrete
overlay on I-43 over the Fox River, Atkinson Drive over I-43, and Military Avenue
over I-43; replacing the bridge joints along I-43 over the Fox River and
Military Avenue over I- 43; painting of the steel girders within ten feet of
the joint replacements, the box girders along the arch span, and all steel
within the splash zone along I-43 over the Fox River; concrete pavement repairs
along I-43 between Webster Avenue and Military Avenue and along with the ramps
at Webster Avenue and Atkinson Drive; traffic cameras at I-43/Danz Avenue, I-
43/University Avenue, and I-43/County JJ; dynamic message signs at
I-43/Glenmore Road, I- 43/Danz Avenue, I-43/Military Avenue, and I-43/WIS
54/57; ramp gates at the Webster Avenue and Atkinson Drive on-ramps to I-43;
temporary and permanent storm sewer; beam guard replacement; median concrete barrier
wall; sign replacement; and pavement markings.
October 1 to October 5: Contractor
continued work on the modular joints, they continued blast cleaning and
painting the outside steel girders, they finished the parapet wall surface
repair, and they finished replacing the pins and hangers along I-43 southbound
over Leo Frigo Bridge.
October 8 to October 12: Contractor will
continue work on the modular joints and blast cleaning and painting the outside
steel girders along I-43 southbound over Leo Frigo Bridge; they will switch
traffic to be directional along the Atkinson Drive southbound lanes and will
begin work on the deck surface along the Atkinson Drive northbound lanes; and
they began placing the final pavement marking throughout the project limits.
Traffic Impacts: I-43 northbound and
southbound is now bi-directional along the I-43 northbound lanes. The on-ramp
from Webster Avenue to I-43 northbound, the on-ramp from Atkinson Drive to I-43
southbound, and the off-ramp from I-43 southbound to Webster Avenue are closed
to all traffic. Starting October 8, traffic along Atkinson Drive will be
reduced to one lane in each direction and will be counter-directional along the
southbound lanes between the railroad overpass and Hurlbut Street.
US 41 Orange Lane to Glory Road, Main Avenue
(County G) Interchange
Schedule: March 2012 through June 2013.
The Main Avenue (County G) interchange will be closed for 60 consecutive days
beginning September 17, 2012.
Length: Mainline -3.5 miles (Orange Lane -
Glory Road); Main Avenue (County G) - 0.5 miles (Spirit Way - Lawrence Drive)
Cost: $57 million
Location: Town of Lawrence, city of De Pere,
village of Ashwaubenon; Brown County
Description of project: This project will
reconstruct US 41 Mainline between Orange Lane and Glory Road and the
reconstruction of the Main Avenue interchange and replacement of bridges over
Ashwaubenon Creek, Main Avenue, and Grant Street.
October 1 to October 5: The contractor will
begin outside mainline grading and structure work made available after the
switch to stage 2. Retaining wall work will continue along the Ashland
Avenue ramp. Work on the barrier wall and shoulders of this ramp will
also continue. On County G, aggregate placement, concrete placement,
storm sewer, and sign structure work will continue.
October 8 to October 12: The contractor
will continue outside mainline grading and structure work from Orange Lane to
Glory Road. On County G, the contractor will continue placing concrete
pavement and curb and gutter. Work will begin on County EE bridges and
retaining walls.
Traffic impacts: US 41 northbound and
southbound shoulders closed from March 5, 2012 to June 21, 2013 from 1.5 miles
south of Scheuring Road to Parkview Road. US 41 northbound and southbound
lanes are restricted to 11 feet from 1.5 miles south of Scheuring Road to
Parkview Road with speeds reduced from 65 mph to 55 mph within the project
limits and north through the Mason Street Interchange project. As of
March 27, east and westbound traffic on County G are reduced to one
lane each direction. Beginning on September 17 at midnight, the
County G interchange will close for 60 days. The closure will include the
north and southbound on/off ramps to US 41, as well as County G itself from
just west of the Mid Valley Drive intersection to a point just west of the
Lawrence Drive intersection. Mid Valley Drive will also be closed at County G
with no access to County G. The left shoulder of the northbound off-ramp to
Oneida Street will be closed until October 19. The left lane of the
southbound off-ramp to Scheuring Road will be closed until October 12.
County EE (Grant Street) will be closed under US 41 on October 3, 4, 9, and 10
from 9 p.m. to 5 a.m. Both shoulders of Glory Road from US 41 to 1000
feet in both directions will be closed until October 19. The northbound and
southbound outside lanes will be closed from 8 p.m. to 5 a.m. on the night of
October 3. The southbound outside lane will be closed from 8 p.m. to 5
a.m. on the nights of October 5, October 8 through 13, and October 15 and
20. The southbound on-ramp for Ashland Avenue will be closed from 8 p.m.
to 5 a.m. on the night of October 5.
US 41 (Early Structures/Early Fills), (Beaver
Dam Creek Box Culvert at Van Boxtel), (Wetland Mitigation Site Resort Road) –
US 41 major
Schedule: June 2011 to October
2012
Length: 0.8 Miles
Cost: $38.2 million
Location: US 41/WIS 29
Interchange, County J - village of Suamico
Description: The work under this
contract consists of common excavation; borrow excavation, construction of
various structures, storm sewer, culverts, and erosion control.
October 1 to October 5: Continue forming and
pouring anchor slabs and parapets. Continue to place miscellaneous storm sewer
pipes and manholes. Continue staining the pre-stressed concrete panels.
Continue final restoration where staging allows.
October 8 to October 12: Continue forming and
pouring last remaining parapets. Continue staining the pre-stressed concrete
panels. Continue final restoration and work on punch list items.
Traffic Impacts: No more traffic
impacts all major work is complete.
US 41/ WIS 29 Interchange Core Project - US
41 major
Schedule: August 2012 to October 2014
Length: 1.6 miles along US 41, 0.8 miles
along WIS 29
Cost: $97 million
Location: US 41 (Mason Street to Memorial
Drive)/ WIS 29 (County J to Taylor Street)
Description: This project will
complete the reconstruction of the US 41 and WIS 29 interchange, converting the
interchange by building high speed, free flow flyover ramps, along with adding
capacity to US 41. Included in this project is the construction of 12 bridges,
15 retaining walls, 30 sign bridges, concrete pavement, asphalt pavement, storm
sewer, stormwater detention ponds and landscaping, while incorporating many
community sensitive design features.
October 1 to October 5: Crews will continue
bridge pier construction in the US 41 median south of Shawano Avenue and north
of Dousman Street, along with pier construction along the east side of US 41
between Larson Road and Shawano Avenue. Crews will continue the construction of
soil improvements along the east and west side of US 41 north of Memorial
Drive. At night crews will continue widening the median to allow for
temporary pavement, as well as some pours at night at the median flyover bridge
piers. Crews will continue removing pavement and installing drainage
blanket in the old WIS 29 areas, along with wick drain installation. Traffic
will be shifted toward the median on northbound and southbound US 41 to allow
for the construction of the new US 41 bridges over Memorial Drive. Bridge crews
have also began the construction of the piers at the new WIS 29 bridges over
Packerland Drive.
October 8 to October 12: Crews will continue
bridge pier construction in the US 41 median south of Shawano Avenue and north
of Dousman Street, along with pier construction along the east side of US 41
between Larson Road and Shawano Avenue. Crews will continue the construction of
soil improvements along the east and west side of US 41 north of Memorial
Drive. Retaining wall crews will continue construction of the retaining
wall on the east side of US 41, from the south project limits to Larson Road.
At night crews will continue widening the median to allow for temporary
pavement, as well as some pours at night at the median flyover bridge
piers. Crews will continue removing pavement and installing drainage
blanket in the old WIS 29 areas, along with wick drain installation. Bridge
crews will also continue the construction of the piers at the new WIS 29
bridges over Packerland Drive.
Traffic Impacts: Lane closures are
scheduled for US 41 northbound and southbound traffic Tuesday through Friday
nights.
US 41/WIS 29/County J Structures and County
RK (South Frontage Road) West
Schedule: June 2011 to August
2012
Length: 1.1 Miles
Cost: $10 million
Location: WIS 29/County J and
WIS 29 South Frontage Road, County J to Duck Creek
Description: Work consists of
building new structures along WIS 29 at County J with aesthetic details and
under deck lighting; reconstructing County J from Berkshire Drive to Shawano
Avenue to go under WIS 29 with street lighting, sidewalks, and plantings;
constructing a single lane roundabout at the intersection of County J and new
County RK (South Frontage Road); and constructing a new urban roadway (County
RK) with sidewalk along the south side of the roadway, street lighting, and
plantings.
October 1 to October 5: Contractor finished
staining the concrete surfaces along the bridges and retaining wall and they
completed the final landscaping along County J.
October 8 to October 12: Contractor will
install the final plantings throughout the County J and County RK roundabout.
Traffic Impacts: Shoulders closures
along County J under WIS 29.
WIS 29 - County EB Ramps, County RK Park and
Ride, Duck Creek Bridges
Schedule: February to November
Length: 2 miles total at various locations
adjacent to the WIS 29/US 41 interchange
Cost: $18 million
Location: Green Bay, WI, Brown
County
Description: Project includes the
construction of the eastbound and westbound County EB on and off ramps at WIS
29, widening of WIS 29 eastbound and westbound, building structures over Duck
Creek, construction of Shawano Avenue and temporary connections at Dousman and
the US 41 ramp terminals at Shawano Avenue, temporary ramps at US 41 and
Shawano Avenue, realignment of Beaver Dam Creek, and a Park and Ride at County
RK.
October 1 to October 5: Aggregate
placement will occur west of Duck Creek. Construction of the Duck Creek
bridge abutments will begin. Storm sewer installation will continue, and gravel
will be placed at the Shawano Avenue connection. Curb and gutter will also
be installed at the Shawano Avenue connection.
October 8 to October 12: Work will
finish digging Beaver Dam Creek for realignment. Work will continue on
the piers in Duck Creek. Asphalt base will be placed west of Duck Creek.
Work will begin to remove the railroad tracks on County EB south of County
RK. Vane drain installation will occur.
Traffic Impacts: There will be
daily inside lane closures on WIS 29 west of County EB/Packerland Drive. There
will be also be various shoulder and lane closures on WIS 29 next week during
the day and evening. Expect daily westbound and eastbound WIS 29 lane
closures. There were many changes in pavement marking, barrier wall, signing,
and traffic patterns that occurred in the beginning of the week on WIS 29,
County EB (Packerland Drive/ /Cardinal Lane), Dousman Street, Shawano Avenue,
and the US 41 ramps. The traffic pattern adjacent to the Cardinal/Packerland/County
EB and WIS 29, as well as US 41 and Dousman/Shawano has changed considerably.
Please drive with caution, and plan for slight delays accordingly. There
will be outside lane closures on Packerland Drive/County EB on Tuesday night at
the railroad tracks to begin track removal. These closures will be
allowed between the hours of 6 p.m. Tuesday night and 6a.m. Wednesday morning.
Mason Street Interchange and 9th
Street to Larsen Road Mainline - US 41 major
Schedule: September 2011 to October 2012
Length: 1.0 Mile
Cost: $29 million
Location: Mason Street Interchange and US 41
Mainline from 9th Street to Larsen Road.
Description: This project will reconstruct
the Mason Street Interchange with new ramps, bridge over US 41, roundabout ramp
terminals, and retaining walls. The project also includes the complete
reconstruction of the US 41 mainline through the Mason Street Interchange
vicinity, from just south of 9th Street to just south of Larsen
Road. Mainline includes the paving of mainline to the ultimate roadway section
including the replacement of the 9th Street bridges, box culverts,
retaining walls, and storm sewer. The project further includes the razing and
removal of the Allied Pool building and subsequent construction of a detention
pond on that site.
October 1 to October 5: Minor work will
continue on the structures, retaining walls and electrical/lighting
installations. General landscaping and finishing work will continue.
October 8 to October 12: Minor work continues
on the structures, retaining walls and electrical installations.
Landscaping and finish work continue.
Traffic impacts: US 41 and
Mason Street are open to traffic. There are no anticipated traffic
impacts for the week October 8 to October 12.
Temporary Signals- Packerland Drive/ Dousman
Street/ Shawano Avenue
Schedule: November 2011 to October 16, 2015
Length: Nine intersections
Cost: $516,000
Location: Packerland Drive/ Dousman Street/
Shawano Avenue Intersections - Green Bay, WI
Description: This contract shall
consist of installing and operating temporary traffic signals and all
incidental items.
Traffic impacts: No traffic impacts -
work being done off alignment.
Velp Avenue (US 141), City of Green Bay
Schedule: April 2012 to
September 2012
Length: 1.7 Miles
Cost: $6.1 million
Location: Velp Avenue from
Norwood Avenue to Military Avenue, Atkinson Drive from Velp Avenue to the I-43
Interchange
Description: Work consists of
grading, storm sewer, base aggregate dense, concrete pavement, asphalt
pavement, concrete sidewalk, wall modular block gravity, pavement marking and
the construction of a roundabout at the intersection of Atkinson Drive and Velp
Avenue.
October 1 to October 5: The
contractor poured sidewalk, installed street lighting, and placed topsoil.
October 8 to October 12: The
contractor will be installing landscaping and trees, paving asphaltic driveways
and parking lots.
Traffic Impacts: Velp Avenue traffic
will be reduced to the one lane in both northbound and southbound directions
from Military Avenue to Norwood Avenue. Atkinson Drive will be reduced to one
lane in both the westbound and eastbound directions from Velp Avenue to the Interstate
43 interchange. All side roads along Velp Avenue from Military Avenue to
Norwood Avenue will remain open to traffic.
WIS 96 (Wrightstown)
Schedule: September 10, 2012 to
October 22, 2012
Length: 2.1 Miles
Cost: $1.1 million
Location: WIS 96, Shanty Road
to Lagoon Road
Description: This project
involves asphalt pavement milling, asphalt pavement overlay, shoulder widening,
guardrail replacement, terminal upgrades, culvert pipe replacement, and
pavement marking.
October 1 to October 5: The contractor
completed shoulder grading and re-ditching along WIS 96. Asphalt paving
continued on eastbound and westbound lanes of WIS 96. Pavement marking
and restoration of slopes continued.
October 8 to October 12: The contractor will
continue paving mainline WIS 96 and begin sideroad/driveway tie-ins.
Shoulder shaping will continue along eastbound and westbound WIS 96. Work
will begin on the installation of new guardrail along shoulders.
Traffic impacts: During paving
operations traffic will be reduced to one lane with flagging. Access will
be maintained to local businesses, residences and side road cross traffic
throughout the project. Shoulders along eastbound and westbound WIS 96
will remain closed for the duration of the project.
Brown/Outagamie
County
WIS 54
Schedule: April 2012 to
mid-November 2012
Length: 1.0 Miles
Cost: $8.74 million
Location: WIS 54 from Oneida to
Green Bay, County U to WIS 172
Description: This project
involves the realignment of WIS 54 with a new bridge over Duck Creek and
construction of a roundabout at the intersection of WIS 54 and Seminary
Road. Work includes storm sewer, asphalt pavement, construction of a
retaining wall, bridge rehabilitation, lighting, signing, landscaping and
pavement marking.
October 1 to October 5: Crews continued
grading operations along WIS 54. Strom sewer continued through the week along
WIS 54. Landscaping crews began placing topsoil and started seeding along the
length of the project. Staining work continued on the abutments of the
new structure of WIS 54 over Duck Creek. Rehabilitation work began on the old
structure of WIS 54 over Duck Creek. Electrical work continued for the
pedestrian paths along WIS 54 and at roundabout at the intersection of WIS 54
and Seminary Road.
October 8 to October 12: Grading
operations along WIS 54 will continue through the week. Storm sewer will
be placed early in the week along portions of WIS 54. Landscape crews will
continue to place topsoil and seed along WIS 54. Rehabilitation work on
the old structure of WIS 54 over Duck Creek will continue through the week.
Electrical work will continue along the pedestrian paths through the
week.
Traffic Impacts: Traffic along
WIS 54 will remain open at all times, although brief periods of flagging may
occur that will cause delays to the traveling public. An all-way stop
condition is in place for the intersection of WIS 54 and Seminary Road.
Traffic along WIS 54 is shifted to the north to allow for construction on the
new lanes of WIS 54 and the south portion of the roundabout at the intersection
of WIS 54 & Seminary Road. Please note traffic is now routed over the new
structure of WIS 54 over Duck Creek. Portions of WIS 54 have been reduced
to 10-foot lanes to allow for construction activities. The south leg of
Seminary Road is closed to thru traffic and will remain closed until late
October for the construction of the WIS 54 and Seminary Road roundabout. West
Service road is closed and will remain closed until mid to late October.
Calumet County
US 10/City of
Brillion
Schedule: April 2012 to October 2012
Length: 1.9 miles
Cost: $6.0 million
Location: County HR to eastern city limits –
Brillion
Description: The project is an
urban reconstruct project involving earthwork excavation, base aggregate,
asphalt pavement, concrete pavement, sanitary sewer, storm sewer, curb and
gutter, pavement marking, permanent signing, signals, and landscaping.
October 1 to October 5: Pavement removals,
grading and placement of breaker run and base aggregate will continue between
County HR and the un-named tributary to Spring Creek. Concrete paving has
started in the westbound lane from Columbus Avenue to Northway Drive.
October 8 to October 12: The contractor is
scheduled to begin concrete pavement preparation from Columbus Avenue to
Northway Drive in the eastbound lane after traffic is switched to the new
concrete pavement. Removals, grading, breaker run and base aggregate is
scheduled between County HR and the un-named tributary to Spring Creek.
Sidewalk, driveway and intersection work on the north half of US 10 is
scheduled to begin between Columbus Avenue and Northway Drive.
Traffic impacts: The project is closed
to through traffic. A detour route is in place. The detour route will follow US
10 to WIS 57 to County K to County PP to US 10. One-Way westbound access
will be maintained to local businesses and property owners.
Calumet/Manitowoc
County
Region-wide rumble
strip retrofit
US 10
Schedule: October 1, 2012 until November 2, 2012
Length: Approx 34 miles
Cost: $1.8 million (total for awarded contract)
Location: County N to I-43
October 5 to October 6: Installation of
centerline rumble strips
October 8 to October 13: Complete the
installation of rubble strips, and begin joint sealing and Installation of
pavement marking
Traffic impacts: Work will be
conducted under a flagged rolling lane closure from 7 a.m. to 7 p.m. Traffic
should be prepared for delays.
Door
County
Region-wide rumble
strip retrofit
WIS 42
Schedule: September 24, 2012 until November 2,
2012
Length: Approx 16
miles
Cost: $1.8 million (total for awarded contract)
Location: Egg Harbor – Sturgeon Bay
October 4 to October 5: Installation of
centerline rumble strips
October 8 to October 12: Joint sealing and the
installation of pavement markings
Traffic impacts: Work will be
conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m.
– 7 p.m., and Fridays 7a.m. – noon. Traffic should be prepared for delays.
Fond du Lac County
WIS 67
Auburn Lake Creek Culvert
Schedule: July 17 to October 2012
Length: 0.29 miles
Cost: $634,000
Location: Birchwood Drive – County G, Fond du Lac County
Description: Primary work to be performed includes box culvert and retaining wall construction, grading, asphaltic paving and guardrail at structure approaches.
Auburn Lake Creek Culvert
Schedule: July 17 to October 2012
Length: 0.29 miles
Cost: $634,000
Location: Birchwood Drive – County G, Fond du Lac County
Description: Primary work to be performed includes box culvert and retaining wall construction, grading, asphaltic paving and guardrail at structure approaches.
October 1 to October 5: Crews completed
asphalt paving and placement of shoulder material. Crews continuing concrete
barrier wall construction.
October 8 to October 12: Crews are scheduled
to install beam guard, place permanent erosion control and pavement marking.
Traffic Impact: WIS 67 will be closed
to through traffic beginning July 17. Detour route will be County SS to County
G.
WIS 175
Parson’s Creek Culverts
Schedule: July 17 to October 2012
Length: 0.13 miles
Cost: $391,000
Location: County B (East) – Lost Arrow Rd, Fond du Lac County
Description: Primary work to be performed includes construction of box culverts, grading, asphaltic paving and guardrail at structure approaches.
September 24 to September 28: Crews continued construction of the box culvert.
Parson’s Creek Culverts
Schedule: July 17 to October 2012
Length: 0.13 miles
Cost: $391,000
Location: County B (East) – Lost Arrow Rd, Fond du Lac County
Description: Primary work to be performed includes construction of box culverts, grading, asphaltic paving and guardrail at structure approaches.
September 24 to September 28: Crews continued construction of the box culvert.
October 1 to October 5: Crews are scheduled
to continue box culvert construction, place riprap and backfill structure
October 1 to October 5: Crews continued
construction of the box culvert.
October 8 to October 12: Crews are scheduled
to continue box culvert construction, place riprap and backfill structure.
Traffic Impact: WIS 175 will
be closed to through traffic beginning July 17. Detour route will be County B
to US 41 to US 151.
Marinette County
Region-wide rumble
strip retrofit
US 141/ US 8
Schedule: September 24, 2012 until November 2,
2012
Length: Approx 20 miles
Cost: $1.8 million (total for awarded contract)
Location: Wisconsin-Michigan State line to
County R; County K to Division St. (Wausaukee)
October 1 to October 5: Installation of
pavement marking
October 8 to October 12: Installation of
pavement marking
Traffic impacts: Work will be
conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m
.– 7 p.m., and Fridays 7a.m. – noon. Traffic should be prepared for
delays.
US 41
Schedule: June 11, 2012 to October 10, 2012
Length: 2.1 miles
Cost: $3.8 million
Location: South Doland Avenue to Old Peshtigo Road, City
of Peshtigo,
Marinette County
Description: This project involves the removal and replacement of
the existing bridge over the Peshtigo River. Also included is milling of the
existing asphalt roadway and paving asphalt pavement at the same depth.
Existing concrete pavement on the east side of the city will be diamond ground
to provide a better riding surface. Existing sidewalk ramps are being replaced.
October 1 to September 5: Structure crews will continue work on the parapets
on the bridge. Curb and gutter will be placed on the roadway on either side of
the bridge. Electrical conduit will be installed behind the curb and gutter.
New sidewalk will be poured late in the week on the roadway approaches to the
bridge.
October 8 to October 12: Concrete sidewalk will be finished early in the
week. The asphalt pavement on the approaches to the bridge will be placed
during the early/mid portions of the week followed by pavement marking.
Structure crews will clean-up the bridge deck and install the railing on the
bridge.
Traffic impacts: US 41 will be closed between Front Street and
Pine Street in the city of Peshtigo for the duration of the project for
bridge construction. Recommended alternate route is to use US 41 bypass of
Peshtigo via the County Y and Business 41 ramps. The intersection of US 41 and
Pine Street will be closed during work activities at the intersection. The
alternate route will be to use Beebe Avenue between Pine Street and US 41.
US 141
Schedule: May 21, 2012 to
October, 2012
Length: 6.5 miles
Cost: $3.9 million
Location: Amberg to Beecher,
Marinette County
Description: This
project involves the pulverizing and re-laying of 6.5 miles of US 141 from Amberg
to Beecher, including the addition of a northbound and southbound passing
lanes, intersection improvements, and culvert replacements. This project also
includes new pavement, concrete curb and gutter, sign replacement, and pavement
marking.
Sept 30 to Sept 06: The contractor
is working on pavement markings and punch list items.
Oct 07 to Oct 13: The contractor will
be working on punch list items.
Traffic impacts: US 141 will be
maintained under the guidance of standard flagging operations, but will be open
to through traffic during construction operations, throughout the duration of
the project.
Manitowoc County
US 151/ I-43
Schedule: August to October
Length: N/A miles
Cost: $580,000
Location: US 151 and I-43 Interchange
Description of project: The work under this
contract consists of widening the southbound and northbound entrance ramps,
various pavement repair and replacement on all four ramps at the interchange
and median work on US 151.
.October 1 to October 6: contractor will
be paving asphalt shoulder on northbound US 151. Contractor will be installing
concrete pavement in ramp widening areas. Contractor will also be
completing electrical installations. New pavement markings will be
placed. Site restoration will begin.
October 8 to October 12: Contractor will
continue installing concrete pavement in ramp widening areas. New
pavement markings will be placed. Site restoration and clean up will be
done. Contractor will install new signage.
Traffic impacts: US 151 will be
restricted to at least one 12-foot-wide lane in each direction on the overpass.
Ramp widths will be restricted to 12-foot-wide lanes once the ramp work begins.
There will be no impacts on the I-43 through traffic.
Oconto
County
WIS 22
Schedule: June 4 to mid-November
Length: Eight miles
Cost: $7.4 million
Location: Gillett to Oconto
Falls
Description: The highway is being
reconstructed between Gillett and Oconto Falls. Additionally, a
single-lane roundabout will be built at the WIS 22/32 intersection.
October 1 to October 5: Contractor continued
paving mainline and intersections from Gillett to Oconto Falls.
Contractor installed electrical conduit and concrete bases at WIS 22/32
roundabout and WIS 22/32 West Junction.
October 8 to October 12: Contractor will
continue paving mainline and intersections from Gillett to Oconto Falls.
Contractor will begin to place final shoulder gravel from Gillett to Oconto
Falls. Contractor will complete traffic lighting and electrical
installations at WIS 22/32 roundabout and WIS 22/32 West Junction.
Traffic impacts: WIS 22 is closed from
Gillett to Oconto Falls. This closure will close both WIS 22 and WIS 32 to
through traffic and the detour is posted. Going north on WIS 22, the
detour will start at County C in Pulcifer to County E, US 141, and WIS
22. Going south, it is the same route in reverse. Northbound on WIS
32, the detour will start at County E, County C, WIS 22, and WIS 32 in
Gillet. Going south, it is the same route in reverse. Access will
be maintained to local businesses, residences and side road cross traffic
throughout the project.
Region-wide rumble
strip retrofit
WIS 32
Schedule: September 24, 2012 until November 2,
2012
Length: Approx 40
miles
Cost: $1.8 million (total for awarded contract)
Location: Forest/ Oconto County line - Gillett
October 1 to October 6: Joint sealing and
installation of pavement marking
October 8 to October 12: Continue with the
installation of pavement markings
Traffic impacts: Work will be
conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m.
– 7 p.m., and Fridays 7a.m. – 3 p.m. Saturdays 7 a.m. – 5 p.m. Traffic
should be prepared for delays.
Outagamie
County
WIS 55
Schedule: July to November
Length: 0.2 miles
Cost: $1.3 million
Location: WIS 55 and County CE Intersection
Description of project: The work under this
contract consists of constructing a multilane roundabout at the intersection of
WIS 55 and County CE.
October 1 to October 5: The contractor
placed asphalt on the west half of the intersection. Underground
electrical installation continued. Sidewalk construction began on the
west half of the intersection. Preparation for the next traffic stage
also began.
October 8 to October 12: The traffic
will be switched to next stage, at which time the intersection will be
operating as a single lane roundabout. Temporary pavement will be removed on
the north and south sides of the intersection and curb and gutter will be
finished. Curb and gutter and pavement will be placed in the center
circle of the roundabout. One single night closure will be occurring
during this week.
Traffic impacts: WIS 55 will be
restricted to one lane in each direction for the duration of the project.
County CE will be closed at the intersection. Traffic on County CE has access
to WIS 55 from the east while traffic from the west does not. The marked detour
route is County CE to County N to County KK to County GG to County CE. Access
will be maintained to local businesses and residents. Traffic will be switched
early next week. At that time, the intersection will be operating as a single
lane roundabout. There will be a one night closure of the entire intersection
during the week.
WIS 96 (Draper Street, City of Kaukauna)
Schedule: Early April to October 2012
Length: 0.9 miles
Cost: $2.3 million
Location: West Kaukauna City Limits to WIS 55
(Lawe Street)
Description of project: This project will
reconstruct WIS 96 (Draper Street/Taylor Street) between the west Kaukauna city
limits and WIS 55 (Lawe Street). This reconstruction includes new concrete
pavement, concrete curb and gutter, storm sewer, grading, sidewalk, pavement marking,
and signing. Stage 1 work will be from Hayes Street to Desnoyer
Street.
October 1 to October 5: Landscaping
and signing work was done by the contractor. Pavement marking was also
started. The contractor also worked on clean-up and punchlist items.
October 8 to October 12: The contractor will
be placing pavement marking and working on clean-up and punchlist items.
Traffic impacts: WIS 96 (Draper
Street/Taylor Street) will be closed to thru traffic from Hayes Street to
Desnoyer Street. Business access will be maintained via side streets. The
marked detour will be via County N, County OO, and WIS 55.
Region-wide rumble
strip retrofit
WIS 15
Schedule: September 24, 2012 until November 2,
2012
Length: Approx 14 miles
Cost: $1.8 million (total for awarded contract)
Location: US 45 to Greenville
October 1 to October 5: Installation of
centerline and shoulder rumble strips and begin joint sealing
October 8 to October 12: Continue joint
sealing and installation of pavement markings
Traffic impacts: Work will be
conducted under a flagged rolling lane closure Monday – Friday 9 a.m. to 3
p.m., Traffic should be prepared for delays.
Region-wide rumble
strip retrofit
WIS 47
Schedule: September 24, 2012 until November 2,
2012
Length: Approx 10 miles
Cost: $1.8 million (total for awarded contract)
Location: County B to Mackville
October 1 to October 5: Installation of
centerline and shoulder rumble strips and begin joint sealing
October 8 to October 12: Continue joint
sealing and installation of pavement markings
Traffic impacts: Work will be
conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m.
– 7 p.m., and Friday 7a.m. – noon. Traffic should be prepared for delays.
Sheboygan County
WIS 57/WIS 23
Schedule: August 2012 to October 2012
Length: 24 Miles
Cost: $1.6 million
Location: Sheboygan County – Ozaukee/Sheboygan
County Line to Manitowoc/Sheboygan County Line
October 1 to October 5: Work continued
on the WIS 57 northbound bridge deck replacement over the Onion River.
Work also continued on the WIS 23 eastbound bridge over the Sheboygan. At
the Intersection of WIS 57 and County C storm sewer installation and grading
were completed
October 7 to October 12: Work will
continue on the WIS 57 northbound bridge deck replacement over the Onion River.
Work will also continue on the WIS 23 eastbound bridge over the Sheboygan
River. At the intersection of WIS 57 and County C concrete curb and
gutter and concrete pavement will be placed.
Traffic impacts:
·
WIS
57 is open to through traffic.
·
WIS
57 has single lane closures in place near the intersection of County C.
·
The
intersection of WIS 28/57/County V has these restrictions:
o
WIS
28 eastbound will be closed at WIS 57. Motorists will continue to have complete access up to
the intersection of WIS 28 and WIS 57 from the west, but will be unable to make
left turn on to WIS 57 north, continue east on WIS 28, or continue east on
County V. WIS 28 eastbound traffic will be able to make a right turn on to WIS
57 southbound. WIS 28 traffic coming from the west and heading east
wanting to access WIS 57 northbound or continue on WIS 28 eastbound will be
detoured from WIS 28 to County W to WIS 57.
o
Traffic
will be unable to turn left onto WIS 28 westbound from WIS 57 northbound.
(Traffic will be able to access WIS 28 westbound from WIS 57 southbound.)
o
Traffic
will be unable to access WIS 57 from County V westbound
o
Traffic
will be unable turn left onto County V eastbound from WIS 57 southbound.
(Traffic will be able to access County V eastbound from WIS 57
northbound.)
·
WIS
23 traffic is restricted to one lane in the eastbound direction near County
TT
Winnebago
County
WIS 21 Interchange and US 41 reconstruction
over Lake Butte des Morts - US 41 major
Schedule: August 2011 to July 2013
Length: 2 miles
Cost: $54.2 million
Location: WIS 21 Interchange, US 41 mainline
from 1500 feet north of Witzel Avenue, to the US 45 Interchange.
Description: This project
involves the reconstruction of the WIS 21 interchange to pass over US
41. The interchange will be completely reconstructed to include
roundabouts at ramp terminals and at the WIS 21 intersections with Washburn and
Koeller Streets. This project also includes the reconstruction of mainline
US 41 from Witzel Avenue to the US 45 Interchange including new bridges over
Lake Butte des Morts and Sawyer Creek. The work on the Lake Butte des Mort
Causeway will include a recreational trail along the east side of US 41
crossing over the water.
September 29 to October 6: Crews continued
building retaining walls on the northeast corner of the WIS 21 interchange and
continue grading for the new northbound US 41 lanes between WIS 21 and US
45. Crews finished pier construction and began girder erection on the
north and south channel bridges for northbound US 41, and began cofferdam
construction at the main channel bridge. Crews continued installing
concrete pavement on the northbound US 41 lanes between Witzel Avenue and Lake
Butte des Morts and on WIS 21 east of US 41. Crews began landscaping the
center roundabout islands at Washburn and Koeller Streets.
October 7 to October 13: Crews will continue
building retaining walls on the northeast corner of the WIS 21 interchange and
continue grading for the new northbound between WIS 21 and US 45. Crews
will continue girder erection and cofferdam construction for the new northbound
US 41 bridges on the Lake Butte des Morts causeway. Crews will finish
installing concrete pavement on the northbound lanes of US 41 between
Witzel Avenue and Lake Butte des Morts as well as on the ramps and roundabout
for the northbound US 41 ramps at WIS 21. Crews will begin sidewalk
installation on WIS 21 east of US 41.
Traffic impacts: The northbound and
southbound shoulders of US 41 are closed between US 45 and Witzel
Avenue. Northbound and southbound US 41 is reduced to two 11-foot lanes in
each direction between US 45 and Witzel Avenue. WIS 21 is closed to
through traffic between US 41 and Koeller Street. The signed detour to
WIS 21 from US 41 will use the WIS 44/WIS 91 interchange. WIS 21 is open
west of US 41 only. Westbound WIS 21 traffic in the city of Oshkosh will
continue to utilize the WIS 44 signed detour for access to US 41.
Eastbound WIS 21 traffic approaching US 41 will utilize southbound US 41 to WIS
44 to access northbound US 41.
US
41 – Mainline (US 45 to Breezewood Lane)
Schedule: March 2011 to June
2013
Length: 8.0 Miles
Cost: $45 Million
Location: US 41 - US 45
Interchange to Breezewood Lane
Description: This project
involves the reconstruction and widening of US 41. The work includes
construction of multiple structures including: bridges, box culverts, and sign
bridges along with grading, base aggregate, concrete & asphalt pavements,
concrete barrier wall, and pavement marking.
September 30 to October 6: Concrete pavement was
completed in all of the driving lanes. There are several areas where the
median pavement will be constructed in the next stage (November). Work
on the median concrete barrier and light pole bases continued from WIS 76 to
County G.
October 7 to October 13: Work will continue in
the median. Crews will be installing light pole bases and barrier wall from
County GG to Breezewood Lane. Work will begin on the outside shoulder of
the new northbound lanes. Crews will begin constructing the asphalt and
gravel shoulders from WIS 76 to Breezewood Lane. Type I (Large) sign
bases and supports will be installed between WIS 76 and Breezewood Lane. Crews
will begin painting the edge lines and installing grooved in contrast tape
skips.
Traffic
impacts:
Trucks are required to use the Left Lane thru the work zone due to the vane
drains in the right lane which cause a bumpy ride. The speed limit for
both northbound and southbound traffic has been reduced to 55 mph and will
remain that way until November 2012. The northbound traffic continues the
temporary lanes. The emergency stopping area for northbound traffic near
Nee-Vin Road has been closed. The emergency stopping area near County GG will
remain open. The on and off ramps to WIS 76 and Breezewood/Bell Street remain
open. Please observe the advisory speed limits posted on the ramps.
0 Comments:
Post a Comment
<< Home