Friday, October 12, 2012

Weekly construction update


(Green Bay) The Wisconsin Department of Transportation (WisDOT) NE Regional Office in Green Bay is providing a weekly update on region construction, which includes the counties of Brown, Calumet, Door, Fond du Lac, Kewaunee, Manitowoc, Marinette, Oconto, Outagamie, Sheboygan, and Winnebago.

                  

Motorists are advised to use caution and remain alert when driving through any work zone.

Drivers are also encouraged to seek information about work zones and detours in the following ways:

  • For statewide, recorded road construction information, 24 hours a day, call 511.

·         For statewide road construction on the World Wide Web, visit www.511wi.gov

 

All work is weather dependent.

 

Brown County

 

Leo Frigo Bridge, city of Green Bay/ I-43

Schedule: May 2012 to July 2013

Length:  3.5 Miles

Cost:  $16.8 million

Location:  I-43 over the Fox River

Description:  Work consists of completing concrete deck surface repair and placing an asphalt or concrete overlay on I-43 over the Fox River, Atkinson Drive over I-43, and Military Avenue over I-43; replacing the bridge joints along I-43 over the Fox River and Military Avenue over I- 43; painting of the steel girders within ten feet of the joint replacements, the box girders along the arch span, and all steel within the splash zone along I-43 over the Fox River; concrete pavement repairs along I-43 between Webster Avenue and Military Avenue and along with the ramps at Webster Avenue and Atkinson Drive; traffic cameras at I-43/Danz Avenue, I- 43/University Avenue, and I-43/County JJ; dynamic message signs at I-43/Glenmore Road, I- 43/Danz Avenue, I-43/Military Avenue, and I-43/WIS 54/57; ramp gates at the Webster Avenue and Atkinson Drive on-ramps to I-43; temporary and permanent storm sewer; beam guard replacement; median concrete barrier wall; sign replacement; and pavement markings.

October 8 to October 12: Contractor continued work on the modular joints and they continued blast cleaning and painting the outside steel girders along I-43 southbound over Leo Frigo Bridge. Contractor also started work on the bridge deck along Atkinson Drive northbound lanes over I-43 by removing the existing concrete overlay, completing surface preparation on the deck, and performing curb repairs.

October 15 to October 19: Contractor will continue work on the modular joints and they will continue to blast cleaning and painting the outside steel girders along I-43 southbound over Leo Frigo Bridge. Contractor will also finish bridge deck preparation and curb repairs along the Atkinson Drive northbound lanes over I-43.

Traffic Impacts: I-43 northbound and southbound is now bi-directional along the I-43 northbound lanes. The on-ramp from Webster Avenue to I-43 northbound, the on-ramp from Atkinson Drive to I-43 southbound, and the off-ramp from I-43 southbound to Webster Avenue are closed to all traffic. Atkinson Drive is reduced to one lane in each direction and is counter-directional along the southbound lanes between the railroad overpass and Hurlbut Street.

 

 

US 41 Orange Lane to Glory Road, Main Avenue (County G) Interchange

Schedule: March 2012 through June 2013.  The Main Avenue (County G) interchange will be closed for 60 consecutive days beginning September 17, 2012.

Length: Mainline -3.5 miles (Orange Lane - Glory Road); Main Avenue (County G) - 0.5 miles (Spirit Way - Lawrence Drive)

Cost: $57 million

Location: Town of Lawrence, city of De Pere, village of Ashwaubenon; Brown County

Description of project: This project will reconstruct US 41 Mainline between Orange Lane and Glory Road and the reconstruction of the Main Avenue interchange and replacement of bridges over Ashwaubenon Creek, Main Avenue, and Grant Street.

October 8 to October 12:  The contractor will continue outside mainline grading and structure work from Orange Lane to Glory Road.  On County G, the contractor will continue placing concrete pavement and curb and gutter.  Work will begin on County EE bridges and retaining walls.

October 15 to October 19:  The contractor will continue outside mainline grading, storm sewer, breaker and aggregate placement as well as structure work on numerous structures made available after the traffic switch to the new inside pavement.  Structure work will specifically involve deck construction and deck pour on the east side of north creek bridge as well as north and south abutment work and deck work on the west side of this same bridge.  Deck construction on the south creek bridge will continue as well as retaining wall work and pile driving on the rest of the bridge structures. On County G, concrete curb and pavement placement will continue.

Traffic impacts: US 41 northbound and southbound shoulders closed from March 5, 2012 to June 21, 2013 from 1.5 miles south of Scheuring Road to Parkview Road.  US 41 northbound and southbound lanes are restricted to 11 feet from 1.5 miles south of Scheuring Road to Parkview Road with speeds reduced from 65 mph to 55 mph within the project limits and north through the Mason Street Interchange project. Beginning on September 17 at midnight, the County G interchange will close for 60 days.  The closure will include the north and southbound on/off ramps to US 41, as well as County G itself from just west of the Mid Valley Drive intersection to a point just west of the Lawrence Drive intersection. Mid Valley Drive will also be closed at County G with no access to County G. The left shoulder of the northbound off-ramp to Oneida Street will be closed until October 19.  The left lane of the southbound off-ramp to Scheuring Road will be closed until October 27.  The shoulders of Glory Road adjacent to the US 41 will be closed till October 27.  The northbound outside lane of US 41 will be closed from 8 p.m. to 5 a.m. the night of October 15 and the southbound outside lane of US 41 will be closed from 8 p.m. to 5 a.m. the night of October 16.

 

US 41 (Early Structures/Early Fills), (Beaver Dam Creek Box Culvert at Van Boxtel), (Wetland Mitigation Site Resort Road) – US 41 major

Schedule: June 2011 to October 2012

Length:  0.8 Miles

Cost:  $38.2 million

Location:  US 41/WIS 29 Interchange, County J - village of Suamico

Description: The work under this contract consists of common excavation; borrow excavation, construction of various structures, storm sewer, culverts, and erosion control.

October 8 to October 12: Continue forming and pouring last remaining parapets. Continue staining the pre-stressed concrete panels. Continue final restoration and work on punch list items.

October 12 to October 16: Continue staining the pre-stressed concrete panels. Continue final grading, restoration and work on punch list items.

Traffic Impacts:  No more traffic impacts all major work is complete.

 

US 41/ WIS 29 Interchange Core Project - US 41 major

Schedule: August 2012 to October 2014

Length: 1.6 miles along US 41, 0.8 miles along WIS 29

Cost: $97 million

Location: US 41 (Mason Street to Memorial Drive)/ WIS 29 (County J to Taylor Street)

Description: This project will complete the reconstruction of the US 41 and WIS 29 interchange, converting the interchange by building high speed, free flow flyover ramps, along with adding capacity to US 41. Included in this project is the construction of 12 bridges, 15 retaining walls, 30 sign bridges, concrete pavement, asphalt pavement, storm sewer, stormwater detention ponds and landscaping, while incorporating many community sensitive design features.

October 8 to October 12: Crews will continue bridge pier construction in the US 41 median south of Shawano Avenue and north of Dousman Street, along with pier construction along the east side of US 41 between Larson Road and Shawano Avenue. Crews will continue the construction of soil improvements along the east and west side of US 41 north of Memorial Drive.  Retaining wall crews will continue construction of the retaining wall on the east side of US 41, from the south project limits to Larson Road. At night crews will continue widening the median to allow for temporary pavement, as well as some pours at night at the median flyover bridge piers.  Crews will continue removing pavement and installing drainage blanket in the old WIS 29 areas, along with wick drain installation. Bridge crews will also continue the construction of the piers at the new WIS 29 bridges over Packerland Drive.

October 15 to October 19: Crews will continue bridge pier construction in the US 41 median south of Shawano Avenue and north of Dousman Street, along with pier construction along the east and west sides of US 41 between Larson Road and Shawano Avenue which will make up the future high speed ramp connection of US 41 and WIS 29. Bridge crews will also continue the construction of the piers at the new WIS 29 bridges over Packerland Drive, as well as begin the construction of the new US 41 structures over Memorial drive by placing temporary shoring. Crews will continue the construction of soil improvements along the east and west side of US 41 north of Memorial Drive.  Retaining wall crews will continue construction of the retaining wall on the east side of US 41, from the south project limits to Larson Road. At night crews will continue widening the median to allow for temporary pavement, as well as some pours at night at the median flyover bridge piers.  Crews will continue removing pavement and installing drainage blanket in the old WIS 29 areas, along with wick drain installation.

Traffic Impacts: Lane closures are scheduled for US 41 northbound and southbound traffic Tuesday through Friday nights.

 

US 41/WIS 29/County J Structures and County RK (South Frontage Road) West

Schedule: June 2011 to August 2012

Length:  1.1 Miles

Cost:  $10 million

Location:  WIS 29/County J and WIS 29 South Frontage Road, County J to Duck Creek

Description:  Work consists of building new structures along WIS 29 at County J with aesthetic details and under deck lighting; reconstructing County J from Berkshire Drive to Shawano Avenue to go under WIS 29 with street lighting, sidewalks, and plantings; constructing a single lane roundabout at the intersection of County J and new County RK (South Frontage Road); and constructing a new urban roadway (County RK) with sidewalk along the south side of the roadway, street lighting, and plantings.

October 8 to October 12: Contractor installed the under deck lighting and completed the final landscaping along County J.

October 15 to October 19: Contractor will complete items on their punch list.

Traffic Impacts: Shoulders closures along County J under WIS 29.

 

WIS 29 - County EB Ramps, County RK Park and Ride, Duck Creek Bridges

Schedule: February to November

Length: 2 miles total at various locations adjacent to the WIS 29/US 41 interchange

Cost: $18 million

Location:  Green Bay, WI, Brown County

Description:  Project includes the construction of the eastbound and westbound County EB on and off ramps at WIS 29, widening of WIS 29 eastbound and westbound, building structures over Duck Creek, construction of Shawano Avenue and temporary connections at Dousman and the US 41 ramp terminals at Shawano Avenue, temporary ramps at US 41 and Shawano Avenue, realignment of Beaver Dam Creek, and a Park and Ride at County RK.

October 8 to October 12:  Work will finish digging Beaver Dam Creek for realignment.  Work will continue on the piers in Duck Creek.  Asphalt base will be placed west of Duck Creek. Work will begin to remove the railroad tracks on County EB south of County RK.  Vane drain installation will occur.

October 15 to October 19:  Panels will be set for the retaining wall on the east side of Duck Creek. Grading will occur at the Shawano Avenue/US 41 ramps area, and at Packerland Drive/WIS 29.  Pier and abutment work will continue on the Duck Creek bridges.  The railroad tracks crossing Packerland Drive, south of County RK, will be removed in stages on Tuesday and Wednesday nights. Traffic will be pushed to the outsides on Tuesday night while work is completed on the inside, and to the inside on Wednesday night as work is completed on the outside.

Traffic Impacts: There will be daily inside lane closures on WIS 29 west of County EB/Packerland Drive. There will be also be various shoulder and lane closures on WIS 29 next week during the day and evening.  Expect daily westbound and eastbound WIS 29 lane closures. There were many changes in pavement marking, barrier wall, signing, and traffic patterns that occurred in the beginning of the week on WIS 29, County EB (Packerland Drive/ /Cardinal Lane), Dousman Street, Shawano Avenue, and the US 41 ramps.  The traffic pattern adjacent to the Cardinal/Packerland/County EB and WIS 29, as well as US 41 and Dousman/Shawano has changed considerably. Please drive with caution, and plan for slight delays accordingly. There will be outside lane closures on Packerland Drive/County EB on Tuesday night at the railroad tracks to begin track removal.  These closures will be allowed between the hours of 6 p.m. Tuesday night and 6a.m. Wednesday morning. The railroad tracks crossing Packerland Drive, south of County RK, will be removed in stages on Tuesday and Wednesday nights.  Traffic will be pushed to the outsides on Tuesday night while work is completed on the insides, and to the inside on Wednesday night as work is completed on the outsides.

 

Mason Street Interchange and 9th Street to Larsen Road Mainline - US 41 major

Schedule: September 2011 to October 2012

Length: 1.0 Mile

Cost: $29 million

Location: Mason Street Interchange and US 41 Mainline from 9th Street to Larsen Road.

Description: This project will reconstruct the Mason Street Interchange with new ramps, bridge over US 41, roundabout ramp terminals, and retaining walls. The project also includes the complete reconstruction of the US 41 mainline through the Mason Street Interchange vicinity, from just south of 9th Street to just south of Larsen Road. Mainline includes the paving of mainline to the ultimate roadway section including the replacement of the 9th Street bridges, box culverts, retaining walls, and storm sewer. The project further includes the razing and removal of the Allied Pool building and subsequent construction of a detention pond on that site. 

October 8 to October 12:  Minor work continues on the structures, retaining walls and electrical installations.  Landscaping and finish work continue.

October 15 to October 19: Minor work will continue on the structures and electrical/lighting installations. General landscaping and finishing work will continue.

Traffic impacts: US 41 and Mason Street are open to traffic. US 41 traffic will be switched to the final project position. Traffic impacts, including lane closers, can be anticipated Monday through Wednesday. Be prepared for changing traffic patterns. 

 

Temporary Signals- Packerland Drive/ Dousman Street/ Shawano Avenue

Schedule: November 2011 to October 16, 2015

Length: Nine intersections

Cost: $516,000

Location: Packerland Drive/ Dousman Street/ Shawano Avenue Intersections - Green Bay, WI

Description: This contract shall consist of installing and operating temporary traffic signals and all incidental items.

Traffic impacts: No traffic impacts - work being done off alignment.

 

Brown/Outagamie County


 

WIS 54

Schedule: April 2012 to mid-November 2012

Length:  1.0 Miles

Cost:  $8.74 million

Location:  WIS 54 from Oneida to Green Bay, County U to WIS 172

Description:  This project involves the realignment of WIS 54 with a new bridge over Duck Creek and construction of a roundabout at the intersection of WIS 54 and Seminary Road.  Work includes storm sewer, asphalt pavement, construction of a retaining wall, bridge rehabilitation, lighting, signing, landscaping and pavement marking.

October 8 to October 12:  Grading operations along WIS 54 continued through the week.  Asphalt paving operations along the new lanes of WIS 54 and the some of the shared use paths were completed throughout the week.  Crews continued placing storm sewer along WIS 54 throughout the week.  Excavation for the East Pond along WIS 54 continued through the week.  Crews continue to complete rehab work on the old structure of WIS 54 over Duck Creek.  Sidewalks along West Service and the roundabout at the intersection of WIS 54 and Seminary road were completed.  Electrical work along the shared use paths along WIS 54 continued throughout the week.

October 15 to October 19:  Grading operations along WIS 54 will continue throughout the week.  Curb and gutter will be placed along the new lanes of WIS 54 early in the week.  Asphalt paving operations along WIS 54 will begin again late in the week.  Excavation for the East Pond along WIS 54 will continue through the week.  Crews will continue rehab work on the old structure of WIS 54 over Duck Creek.  Work will begin on the retaining wall along WIS 54 early in the week.  Electrical work along the shared used paths will continue throughout the weekTraffic Impacts:  Traffic along WIS 54 will remain open at all times, although brief periods of flagging may occur that will cause delays to the traveling public.  An all-way stop condition is in place for the intersection of WIS 54 and Seminary Road.  Traffic along WIS 54 is shifted to the north to allow for construction on the new lanes of WIS 54 and the south portion of the roundabout at the intersection of WIS 54 & Seminary Road. Please note traffic is now routed over the new structure of WIS 54 over Duck Creek.  Portions of WIS 54 have been reduced to 10-foot lanes to allow for construction activities. The south leg of Seminary Road is closed to thru traffic and will remain closed until late October for the construction of the WIS 54 and Seminary Road roundabout. West Service road is closed and will remain closed until mid to late October. 

 

Calumet County

 

US 10/City of Brillion

Schedule: April 2012 to October 2012

Length: 1.9 miles

Cost: $6.0 million

Location: County HR to eastern city limits – Brillion

Description: The project is an urban reconstruct project involving earthwork excavation, base aggregate, asphalt pavement, concrete pavement, sanitary sewer, storm sewer, curb and gutter, pavement marking, permanent signing, signals, and landscaping.

October 1 to October 5:  Pavement removals, grading and placement of breaker run and base aggregate will continue between County HR and the un-named tributary to Spring Creek. Concrete paving has started in the westbound lane from Columbus Avenue to Northway Drive.

October 8 to October 12: The contractor is scheduled to begin concrete pavement preparation from Columbus Avenue to Northway Drive in the eastbound lane after traffic is switched to the new concrete pavement.  Removals, grading, breaker run and base aggregate is scheduled between County HR and the un-named tributary to Spring Creek.  Sidewalk, driveway and intersection work on the north half of US 10 is scheduled to begin between Columbus Avenue and Northway Drive.

Traffic impacts: The project is closed to through traffic. A detour route is in place. The detour route will follow US 10 to WIS 57 to County K to County PP to US 10.  One-Way westbound access will be maintained to local businesses and property owners.

 

Calumet/Manitowoc County

 

Region-wide rumble strip retrofit

US 10

Schedule: October 1, 2012 until November 2, 2012

Length: Approx 34 miles

Cost: $1.8 million (total for awarded contract)

Location: County N to I-43

October 8 to October 12:  Complete the installation of centerline rumble strips, begin joint sealing, and begin installation of permanent pavement markings

October 15 to October 19: Complete joint sealing and continue Installation of permanent pavement markings, installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure from 7 a.m. to 7 p.m. Traffic should be prepared for delays.

 

Door County


 

Region-wide rumble strip retrofit

WIS 42

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 16 miles                                                     

Cost: $1.8 million (total for awarded contract)

Location: Egg Harbor – Sturgeon Bay

October 8 to October 12:  Installation of centerline rumble strips and begin installation of permanent pavement markings

October 15 to October 19:  Complete joint sealing and continue installation of permanent pavement markings, installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Fridays 7a.m. – noon.  Traffic should be prepared for delays.

 

Fond du Lac County

 

WIS 67
Auburn Lake Creek Culvert
Schedule: July 17 to October 2012
Length:  0.29 miles
Cost: $634,000
Location:  Birchwood Drive – County G, Fond du Lac County
Description: Primary work to be performed includes box culvert and retaining wall construction, grading, asphaltic paving and guardrail at structure approaches.

October 8 to October 12: Crews completed barrier wall construction and began beam guard installation.

October 15 to October 19: Crews are scheduled to place pavement marking.

Traffic Impact: WIS 67 will be closed to through traffic beginning July 17. Detour route will be County SS to County G.

 

WIS 175
Parson’s Creek Culverts
Schedule: July 17 to October 2012
Length:  0.13 miles
Cost: $391,000
Location:  County B (East) – Lost Arrow Rd, Fond du Lac County
Description: Primary work to be performed includes construction of box culverts, grading, asphaltic paving and guardrail at structure approaches.
October 8 to October 12: Crews completed box culvert construction, riprap and backfill structure placement.

October 15 to October 19: Crews are scheduled to shape shoulders, install beam guard and place erosion control measures.

Traffic Impact: WIS 175 will be closed to through traffic beginning July 17. Detour route will be County B to US 41 to US 151.

 

 

Manitowoc County

 

US 151/ I-43

Schedule: August to October  

Length: N/A miles

Cost: $580,000

Location: US 151 and I-43 Interchange

Description of project: The work under this contract consists of widening the southbound and northbound entrance ramps, various pavement repair and replacement on all four ramps at the interchange and median work on US 151.

October 8 to October 12: Contractor will complete the installation of concrete pavement in ramp widening areas.  New pavement markings will be placed. Site restoration and clean up will be done.  Contractor will install new signage. New beam guard will be installed.

October 15 to October 19: Contractor will be waiting for cure on the final portion of red concrete before traffic is allowed on it. This portion will remain drummed off and not used until October 19.

Traffic impacts:  Construction will be complete October 12; however, the red ramp widening areas will not be cured enough for traffic until October 19. The only traffic this may affect is oversize/overweight truck traffic.  All other portions of project will be completely open by October 12.

 

Marinette County

 

Region-wide rumble strip retrofit

US 141/ US 8

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 20 miles

Cost: $1.8 million (total for awarded contract)

Location: Wisconsin-Michigan State line to County R; County K to Division St. (Wausaukee)

October 8 to October 12: Complete installation of permanent pavement markings

October 15 to October 19:  Installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Fridays 7a.m. – noon.  Traffic should be prepared for delays.  Please note:  after October 12, lane closures will no longer be required. There will still be work requiring temporary shoulder closures at several locations along this roadway. Traffic is advised to be alert and exercise caution when workers are present.

 

US 41

Schedule:  June 11, 2012 to October 10, 2012

Length:   2.1 miles

Cost:  $3.8 million

Location:  South Doland Avenue to Old Peshtigo Road, City of Peshtigo,

Marinette County

Description: This project involves the removal and replacement of the existing bridge over the Peshtigo River. Also included is milling of the existing asphalt roadway and paving asphalt pavement at the same depth. Existing concrete pavement on the east side of the city will be diamond ground to provide a better riding surface. Existing sidewalk ramps are being replaced.

October 1 to October 5: Structure crews will continue work on the parapets on the bridge. Curb and gutter will be placed on the roadway on either side of the bridge. Electrical conduit will be installed behind the curb and gutter. New sidewalk will be poured late in the week on the roadway approaches to the bridge.

October 8 to October 12: Concrete sidewalk will be finished early in the week. The asphalt pavement on the approaches to the bridge will be placed during the early/mid portions of the week followed by pavement marking. Structure crews will clean-up the bridge deck and install the railing on the bridge.

Traffic impacts: US 41 will be closed between Front Street and Pine Street in the City of Peshtigo for the duration of the project for bridge construction. Recommended alternate route is to use US 41 bypass of Peshtigo via the County Y and Business 41 ramps. It is anticipated that the bridge will be opened to traffic the afternoon of October 12.

 

US 141

Schedule:  May 21, 2012 to October, 2012

Length:   6.5 miles

Cost:  $3.9 million  

Location:  Amberg to Beecher, Marinette County

Description: This project involves the pulverizing and re-laying of 6.5 miles of US 141 from Amberg to Beecher, including the addition of a northbound and southbound passing lanes, intersection improvements, and culvert replacements. This project also includes new pavement, concrete curb and gutter, sign replacement, and pavement marking.

Oct 7 to Oct 13: The contractor is working on punchlist items.

Oct 14 to Oct 20: The contractor will be working on punchlist items.

Traffic impacts:  US 141 will be maintained under the guidance of standard flagging operations, but will be open to through traffic during construction operations, throughout the duration of the project.

 


Oconto County


 

WIS 22

Schedule:  June 4 to October 26

Length:   Eight miles

Cost:  $7.4 million

Location:  Gillett to Oconto Falls

Description: The highway is being reconstructed between Gillett and Oconto Falls.  Additionally, a single-lane roundabout will be built at the WIS 22/32 intersection. 

October 8 to October 12:  Contractor continued paving mainline and intersections from Gillett to Oconto Falls.  Contractor began to place final shoulder gravel from Oconto Falls to WIS 22 / 32 Roundabout.  Contractor completed traffic lighting and electrical installations at WIS 22/32 roundabout and WIS 22/32 West Junction.

October 15 to October 19:  Contractor will continue paving intersections and driveways from Gillett to Oconto Falls.  Contractor will begin installing permanent signs. Contractor will begin installing guardrail.  Contractor will complete placing shoulder gravel from Gillett to Oconto Falls.  Contractor will paint centerline and edge line. 

Traffic impacts:  WIS 22 is closed from Gillett to Oconto Falls. This closure will close both WIS 22 and WIS 32 to through traffic and the detour is posted.  Going north on WIS 22, the detour will start at County C in Pulcifer to County E, US 141, and WIS 22.  Going south, it is the same route in reverse.  Northbound on WIS 32, the detour will start at County E, County C, WIS 22, and WIS 32 in Gillet.  Going south, it is the same route in reverse.  Access will be maintained to local businesses, residences and side road cross traffic throughout the project. 

 

Region-wide rumble strip retrofit

WIS 32

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 40 miles                                                     

Cost: $1.8 million (total for awarded contract)

Location: Forest/ Oconto County line - Gillett

October 8 to October 12:  Continue with the installation of permanent pavement markings

October 15 to October 19:  Complete the installation of permanent pavement markings, installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Fridays 7a.m. – 3 p.m. Saturdays 7 a.m. – 5 p.m.  Traffic should be prepared for delays.

 


Outagamie County


 

WIS 55

Schedule: July to November   

Length: 0.2 miles

Cost: $1.3 million

Location: WIS 55 and County CE Intersection, Kaukauna

Description of project: The work under this contract consists of constructing a multilane roundabout at the intersection of WIS 55 and County CE. 

October 8 to October 12: The intersection was opened as a single lane roundabout on Monday.  The contractor continued operations of pouring concrete sidewalk, pouring curb and gutter, placing topsoil, and final restoration.Temporary pavement was removed to accommodate final surface paving. 

October 15 to October 19:  Final restoration will continue.  All concrete items will be complete.  Pavement marking will begin. 

Traffic impacts:  WIS 55 and County CE will be restricted to one lane in each direction for the remainder of the project with the intersection operating as a single lane roundabout.  The intersection will be closed from 8 p.m., Friday, October 12 until 6 a.m. Saturday, October 13 to accommodate paving the asphalt surface. 

 

WIS 96 (Draper Street, City of Kaukauna)

Schedule: Early April to October 2012   

Length: 0.9 miles

 Cost: $2.3 million

Location: West Kaukauna City Limits to WIS 55 (Lawe Street)

Description of project: This project will reconstruct WIS 96 (Draper Street/Taylor Street) between the west Kaukauna city limits and WIS 55 (Lawe Street). This reconstruction includes new concrete pavement, concrete curb and gutter, storm sewer, grading, sidewalk, pavement marking, and signing.  Stage 1 work will be from Hayes Street to Desnoyer Street. 

October 8 to October 12: The contractor worked on landscaping, clean-up, and punch list items.

October 15 to October 19: The contractor will be working on punch list items.

Traffic impacts:  WIS 96 (Draper Street/Taylor Street) was opened to traffic on Thursday, October 11.

 

Region-wide rumble strip retrofit

WIS 15

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 14 miles

Cost: $1.8 million (total for awarded contract)

Location: US 45 to Greenville

October 8 to October 12: Continue joint sealing and installation of permanent pavement markings

October 15 to October 19:  Complete the installation of permanent pavement markings, installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure Monday – Friday 9 a.m. to 3 p.m., Traffic should be prepared for delays.

 

Region-wide rumble strip retrofit

WIS 47

Schedule: September 24, 2012 until November 2, 2012

Length: Approx 10 miles

Cost: $1.8 million (total for awarded contract)

Location: County B to Mackville

October 8 to October 12: Complete joint sealing and installation of permanent pavement markings

October 15 to October 19: Installation of permanent signs

Traffic impacts: Work will be conducted under a flagged rolling lane closure daily Mondays – Thursdays 7 a.m. – 7 p.m., and Friday 7a.m. – noon.  Traffic should be prepared for delays.

Please note:  after October 12, lane closures will no longer be required. There will still be work requiring temporary shoulder closures at several locations along this roadway. Traffic is advised to be alert and exercise caution when workers are present.

 

Sheboygan County

 

WIS 57/WIS 23

Schedule: August 2012 to October 2012

Length: 24 Miles

Cost: $1.6 million

Location: Sheboygan County – Ozaukee/Sheboygan County Line to Manitowoc/Sheboygan County Line

October 7 to October 12:  Work continued on the WIS 57 northbound bridge deck replacement over the Onion River.  Work also continued on the WIS 23 eastbound bridge over the Sheboygan.  At the intersection of WIS 57 and County C, concrete curb and gutter and concrete pavement was placed.

October 15 to October 19:  Work will continue on the WIS 57 northbound bridge deck replacement over the Onion River. Work will also continue on the WIS 23 eastbound bridge over the Sheboygan River.  At the intersection of WIS 57 and County C, work will continue on placing concrete pavement and work will begin on installing new traffic signals.

Traffic impacts: 

·         WIS 57 is open to through traffic.

·         WIS 57 has single lane closures in place near the intersection of County C. 

·         The intersection of WIS 28/57/County V has these restrictions:

·         WIS 28 eastbound will be closed at WIS 57.  Motorists will continue to have complete access up to the intersection of WIS 28 and WIS 57 from the west, but will be unable to make left turn on to WIS 57 north, continue east on WIS 28, or continue east on County V. WIS 28 eastbound traffic will be able to make a right turn on to WIS 57 southbound.  WIS 28 traffic coming from the west and heading east wanting to access WIS 57 northbound or continue on WIS 28 eastbound will be detoured from WIS 28 to County W to WIS 57. 

·         Traffic will be unable to turn left onto WIS 28 westbound from WIS 57 northbound.  (Traffic will be able to access WIS 28 westbound from WIS 57 southbound.)

·         Traffic will be unable to access WIS 57 from County V westbound

·         Traffic will be unable turn left onto County V eastbound from WIS 57 southbound. (Traffic will be able to access County V eastbound from WIS 57 northbound.)   

·         WIS 23 traffic is restricted to one lane in the eastbound direction near County TT 

 

Winnebago County

. WIS 21 Interchange and US 41 reconstruction over Lake Butte des Morts - US 41 major

Schedule: August 2011 to July 2013

Length: 2 miles

Cost: $54.2 million

Location: WIS 21 Interchange, US 41 mainline from 1500 feet north of Witzel Avenue, to the US 45 Interchange.

Description: This project involves the reconstruction of the WIS 21 interchange to pass over US 41. The interchange will be completely reconstructed to include roundabouts at ramp terminals and at the WIS 21 intersections with Washburn and Koeller Streets. This project also includes the reconstruction of mainline US 41 from Witzel Avenue to the US 45 Interchange including new bridges over Lake Butte des Morts and Sawyer Creek. The work on the Lake Butte des Mort Causeway will include a recreational trail along the east side of US 41 crossing over the water.

October 7 to October 13:  Crews finished building retaining walls on the northeast corner of the WIS 21 interchange and grading for the new northbound US 41 lanes between WIS 21 and US 45.  Crews finished girder erection on the north and south channel bridges for northbound US 41 began deck forming, and continued cofferdam construction at the main channel bridge.  Crews finished installing concrete pavement on the northbound US 41 lanes between Witzel Avenue and Lake Butte des Morts and on WIS 21 east of US 41. 

October 14 to October 20:  Crews will continue deck forming and cofferdam construction for the new northbound US 41 bridges on the Lake Butte des Morts causeway.  Crews will begin installing concrete barrier wall on the northbound lanes of US 41 between Witzel Avenue and Lake Butte des Morts as well as on the ramps and roundabout for the northbound US 41 ramps at WIS 21. Crews will begin landscaping on WIS 21 east of US 41.

Traffic impacts: The northbound and southbound shoulders of US 41 are closed between US 45 and Witzel Avenue. Northbound and southbound US 41 is reduced to two 11-foot lanes in each direction between US 45 and Witzel Avenue.  WIS 21 is closed to through traffic between US 41 and Koeller Street.  The signed detour to WIS 21 from US 41 will use the WIS 44/WIS 91 interchange.  WIS 21 is open west of US 41 only.  Westbound WIS 21 traffic in the city of Oshkosh will continue to utilize the WIS 44 signed detour for access to US 41.  Eastbound WIS 21 traffic approaching US 41 will utilize southbound US 41 to WIS 44 to access northbound US 41.

             

US 41 – Mainline (US 45 to Breezewood Lane)

Schedule: March 2011 to June 2013

Length: 8.0 Miles

Cost: $45 Million

Location: US 41 - US 45 Interchange to Breezewood Lane

Description: This project involves the reconstruction and widening of US 41.  The work includes construction of multiple structures including: bridges, box culverts, and sign bridges along with grading, base aggregate, concrete & asphalt pavements, concrete barrier wall, and pavement marking.

October 7 to October 13: Work continued in the median.  Crews were installing light pole bases and barrier wall from County GG to Breezewood Lane. Work began on the outside shoulder of the new northbound lanes.  Crews constructed the asphalt and gravel shoulders from WIS 76 to Breezewood Lane. Type I (large) sign bases and supports were installed between WIS 76 and Breezewood Lane. Crews began painting the edge lines and installing grooved in contrast tape skips.

October 14 to October 20: Median work on US 41 will continue again this week.  Light bases will be installed between County G and the bridge over the Rail Road Spur.  Barrier wall will continue between County GG and County G. Barrier wall will be installed along the outside of the northbound lanes at County GG and Breezewood Lane. Shoulder work will be completed this week with the final layer of gravel being placed from WIS 76 to Breezewood Lane. Pavement marking will continue in the northbound lanes.  Crews will be painting edge lines and installing grooved in contrast tape skips.

Traffic impacts:   Trucks are required to use the Left Lane thru the work zone due to the vane drains in the right lane which cause a bumpy ride.  The speed limit for both northbound and southbound traffic has been reduced to 55 mph and will remain that way until November 2012.  The northbound traffic continues the temporary lanes. The emergency stopping area for northbound traffic near Nee-Vin Road has been closed. The emergency stopping area near County GG will remain open. The on and off ramps to WIS 76 and Breezewood/Bell Street remain open. Please observe the advisory speed limits posted on the ramps.

0 Comments:

Post a Comment

<< Home